    SUMMARY:

    DoD, GSA, and NASA are issuing a final rule amending the Federal Acquisition Regulation (FAR) to implement changes regarding the retirement of the Past Performance Information Retrieval System and establishment of the Contractor Performance Assessment Reporting System as the official system for past performance information.

    DATES:

    Effective October 10, 2019.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    Mr. Curtis E. Glover, Sr., Procurement Analyst, at 202-501-1448 for clarification of content. For information pertaining to status or publication schedules, contact the Regulatory Secretariat Division at 202-501-4755. Please cite FAC 2019-06, FAR Case 2019-005.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    I. Background

    Effective January 15, 2019, the Past Performance Information Retrieval System (PPIRS) was retired, concluding its merger with the Contractor Performance Assessment Reporting System (CPARS). All data from PPIRS has been merged into CPARS.gov. The transition to a single system provides one location and one account to perform functions such as creating and editing performance and integrity records, changes to administering users, running reports, generating performance records, and viewing/managing performance records.

    II. Discussion and Analysis

    This final rule amends FAR 42.1501 and 42.1503, to establish CPARS as the official system for contractor past performance information. Conforming changes are also made in parts 9, 13, 15, and 25 to remove all references to PPIRS and add CPARS.

    III. Applicability to Contracts at or Below the Simplified Acquisition Threshold (SAT) and for Commercial Items, Including Commercially Available Off-the-Shelf (COTS) Items

    This final rule does not create any new provisions or clauses, nor does it change the applicability or burden of any existing provisions or clauses included in solicitations and contracts valued at or below the SAT, or for commercial items, including COTS items.

    IV. Publication of This Final Rule for Public Comment Is Not Required by Statute

    The statute that applies to the publication of the FAR is the Office of Federal Procurement Policy statute (codified at title 41 of the United States Code). Specifically, 41 U.S.C. 1707(a)(1) requires that a procurement policy, regulation, procedure, or form (including an amendment or modification thereof) must be published for public comment if it relates to the expenditure of appropriated funds, and has either a significant effect beyond the internal operating procedures of the agency issuing the policy, regulation, procedure, or form, or has a significant cost or administrative impact on contractors or offerors. While this final rule relates to the expenditure of appropriated funds, it is not required to be published for public comment because it does not have a significant effect on contractors or offerors (i.e., this action is administrative—it does not require contractors to take any action, affect the way in which contractors retrieve or provide information regarding their performance, or otherwise change policies addressing the assessment or recording of contractor performance). The rule merely reflects the merger of PPIRS into an existing system, CPARS, which now serves as the single official repository for recording and maintaining contractor performance information.

    V. Executive Orders 12866 and 13563

    Executive Orders (E.O.s) 12866 and 13563 direct agencies to assess all costs and benefits of available regulatory alternatives and, if regulation is necessary, to select regulatory approaches that maximize net benefits (including potential economic, environmental, public health and safety effects, distributive impacts, and equity). E.O. 13563 emphasizes the importance of quantifying both costs and benefits, of reducing costs, of harmonizing rules, and of promoting flexibility. This is not a significant regulatory action and, therefore, was not subject to review under section 6(b) of E.O. 12866, Regulatory Planning and Review, dated September 30, 1993. This rule is not a major rule under 5 U.S.C. 804.

    VI. Executive Order 13771

    This rule is not subject to E.O. 13771, because this rule is not a significant regulatory action under E.O. 12866.

    VII. Regulatory Flexibility Act

    Because a notice of proposed rulemaking and an opportunity for public comment are not required to be given for this rule under 41 U.S.C. 1707(a)(1) (see section IV of this preamble), the analytical requirements of the Regulatory Flexibility Act (5 U.S.C. 601 et seq.) are not applicable. Accordingly, no regulatory flexibility analysis is required and none has been prepared.

    VIII. Paperwork Reduction Act

    The Paperwork Reduction Act (44 U.S.C. chapter 35) does apply; however, these changes to the FAR do not impose additional information collection requirements to the paperwork burden previously approved under OMB Control Number 9000-0142, Past Performance Information.

    Start List of Subjects

    List of Subjects in 48 CFR Parts 9, 13, 15, 25, and 42

    • Government procurement
    End List of Subjects Start Signature

    William F. Clark,

    Director, Office of Government-wide Acquisition Policy, Office of Acquisition Policy, Office of Government-wide Policy.

    End Signature

    Therefore, DoD, GSA, and NASA amend 48 CFR parts 9, 13, 15, 25, and 42 as set forth below:

    Start Amendment Part

    1. The authority citation for parts 9, 13, 15, 25, and 42 continues to read as follows:

    End Amendment Part Start Authority

    Authority: 40 U.S.C. 121(c); 10 U.S.C. chapter 137; and 51 U.S.C. 20113.

    End Authority Start Part

    PART 9—CONTRACTOR QUALIFICATIONS

    End Part
    [Amended]
    Start Amendment Part

    2. Amend section 9.104-6, in paragraph (a)(1), by removing “ www.ppirs.gov,, then select FAPIIS” and “Past Performance Information Retrieval System (PPIRS)” and adding “https://www.cpars.gov” and “Contractor Performance Assessment Reporting System (CPARS)” in their places, respectively.

    End Amendment Part
    Start Printed Page 47866
    [Amended]
    Start Amendment Part

    3. Amend section 9.105-1, in paragraph (c) introductory text, by removing “PPIRS” and adding “CPARS” in its place.

    End Amendment Part
    [Amended]
    Start Amendment Part

    4. Amend section 9.105-2, in paragraph (b)(2)(i) introductory text, by removing “ www.cpars.gov,, then select FAPIIS” and adding “https://www.cpars.gov in its place.

    End Amendment Part Start Part

    PART 13—SIMPLIFIED ACQUISITION PROCEDURES

    End Part
    [Amended]
    Start Amendment Part

    5. Amend section 13.106-2, in paragraph (b)(3)(ii)(C) by removing “Governmentwide Past Performance Information Retrieval System (PPIRS) at www.ppirs.gov and adding “Contractor Performance Assessment Reporting System (CPARS) at https://www.cpars.gov in its place.

    End Amendment Part Start Part

    PART 15—CONTRACTING BY NEGOTIATION

    [Amended]
    End Part Start Amendment Part

    6. Amend section 15.407-1, in paragraph (d) introductory text, by removing “PPIRS” and adding “Contractor Performance Assessment Reporting System (CPARS)” in its place.

    End Amendment Part Start Part

    PART 25—FOREIGN ACQUISITION

    [Amended]
    End Part Start Amendment Part

    7. Amend section 25.702-4, in paragraph (c)(3)(vi), by removing “Past Performance Information Retrieval System” and “ www.ppirs.gov and adding “Contractor Performance Assessment Reporting System (CPARS)” and “https://www.cpars.gov in their places, respectively.

    End Amendment Part
    [Amended]
    Start Amendment Part

    8. Amend section 25.703-4, in paragraph (c)(6), by removing “Past Performance Information Retrieval System” and “ www.ppirs.gov and adding “Contractor Performance Assessment Reporting System (CPARS)” and “https://www.cpars.gov in their places, respectively.

    End Amendment Part Start Part

    PART 42—CONTRACT ADMINISTRATION AND AUDIT SERVICES

    End Part Start Amendment Part

    9. Amend section 42.1501 by revising paragraph (b) to read as follows:

    End Amendment Part
    General.
    * * * * *

    (b) Agencies shall monitor their compliance with the past performance evaluation requirements (see 42.1502), and use the Contractor Performance Assessment Reporting System (CPARS) metric tools to measure the quality and timely reporting of past performance information. CPARS is the official source for past performance information.

    Start Amendment Part

    10. Amend section 42.1503 by—

    End Amendment Part Start Amendment Part

    a. Removing from paragraph (a)(1)(iii) “PPIRS” and adding “CPARS” in its place;

    End Amendment Part Start Amendment Part

    b. Revising paragraph (f);

    End Amendment Part Start Amendment Part

    c. Removing from paragraph (g) “PPIRS” and adding “CPARS” in its place; and

    End Amendment Part Start Amendment Part

    d. Removing from paragraph (h)(3) “ http://www.cpars.gov/​,, then select FAPIIS” and adding “https://www.cpars.gov in its place.

    End Amendment Part

    The revision reads as follows:

    Procedures.
    * * * * *

    (f) Agencies shall prepare and submit all past performance evaluations electronically in CPARS at https://www.cpars.gov. These evaluations, including any contractor-submitted information (with indication whether agency review is pending), become available for source selection officials not later than 14 days after the date on which the contractor is notified of the evaluation's availability for comment. The Government shall update CPARS with any contractor comments provided after 14 days, as well as any subsequent agency review of comments received. Past performance evaluations for classified contracts and special access programs shall not be reported in CPARS, but will be reported as stated in this subpart and in accordance with agency procedures. Agencies shall ensure that appropriate management and technical controls are in place to ensure that only authorized personnel have access to the data and the information safeguarded in accordance with 42.1503(d).

    * * * * *
    End Supplemental Information

    [FR Doc. 2019-19362 Filed 9-9-19; 8:45 am]

    BILLING CODE 6820-EP-P

Document Information

Effective Date:
10/10/2019
Published:
09/10/2019
Department:
National Aeronautics and Space Administration
Entry Type:
Rule
Action:
Final rule.
Document Number:
2019-19362
Dates:
Effective October 10, 2019.
Pages:
47865-47866 (2 pages)
Docket Numbers:
FAC 2019-06, FAR Case 2019-005, Item III, Docket No. FAR-2019-0005, Sequence No. 1
RINs:
9000-AN88: Federal Acquisition Regulation (FAR); FAR Case 2019-005, Update to Contract Performance Assessment Reporting System (CPARS)
RIN Links:
https://www.federalregister.gov/regulations/9000-AN88/federal-acquisition-regulation-far-far-case-2019-005-update-to-contract-performance-assessment-repor
Topics:
Government procurement
PDF File:
2019-19362.Pdf
CFR: (9)
48 CFR 42.1501
48 CFR 42.1503
48 CFR 9.104-6
48 CFR 9.105-1
48 CFR 9.105-2
More ...