![]() |
Code of Federal Regulations (Last Updated: July 5, 2024) |
![]() |
Title 48 - Federal Acquisition Regulations System |
![]() |
Chapter 1 - Federal Acquisition Regulation |
![]() |
SubChapter B - Acquisition Planning |
![]() |
Part 11 - Describing Agency Needs |
![]() |
Subpart 11.5 - Liquidated Damages |
§ 11.502 - Procedures.
Latest version.
-
11.502 Procedures.
(a) Include the applicable liquidated damages clause and liquidated damages rates in solicitations when the contract will contain liquidated damages provisions.
(b) Construction contracts with liquidated damages provisions must describe the rate(s) of liquidated damages assessed per day of delay. The rate(s) should include the estimated daily cost of Government inspection and superintendence. The rate(s) should also include an amount for other expected expenses associated with delayed completion such as -
(1) Renting substitute property; or
(2) Paying additional allowance for living quarters.