Code of Federal Regulations (Last Updated: November 8, 2024) |
Title 49 - Transportation |
Subtitle B - Other Regulations Relating to Transportation |
Chapter I - Pipeline and Hazardous Materials Safety Administration, Department of Transportation |
Part 178 - Specifications for Packagings |
Subpart O - Testing of IBCs |
§ 178.801 - General requirements.
-
§ 178.801 General requirements.
(a) General. The test procedures prescribed in this subpart are intended to ensure that IBCs containing hazardous materials can withstand normal conditions of transportation and are considered minimum requirements. Each packaging must be manufactured and assembled so as to be capable of successfully passing the prescribed tests and of conforming to the requirements of § 173.24 of this subchapter at all times while in transportation.
(b) Responsibility. It is the responsibility of the IBC manufacturer to assure that each IBC is capable of passing the prescribed tests. To the extent that an IBC assembly function, including final closure, is performed by the person who offers a hazardous material for transportation, that person is responsible for performing the function in accordance with §§ 173.22 and 178.2 of this subchapter.
(c) Definitions. For the purpose of this subpart:
(1) IBC design type refers to an IBC that does not differ in structural design, size, material of construction, wall thickness, manner of construction and representative service equipment.
(2) Design qualification testing is the performance of the drop, leakproofness, hydrostatic pressure, stacking, bottom-lift or top-lift, tear, topple, righting and vibration tests, as applicable, prescribed in this subpart, for each different IBC design type, at the start of production of that packaging.
(3) Periodic design requalification test is the performance of the applicable tests specified in paragraph (c)(2) of this section on an IBC design type, in order to requalify the design for continued production at the frequency specified in paragraph (e) of this section.
(4) Production inspection is the inspection that must initially be conducted on each newly manufactured IBC.
(5) Production testing is the performance of the leakproofness test in accordance with paragraph (f) of this section on each IBC intended to contain solids discharged by pressure or intended to contain liquids.
(6) Periodic retest and inspection is performance of the applicable test and inspections on each IBC at the frequency specified in § 180.352 of this subchapter.
(7) Different IBC design type is one that differs from a previously qualified IBC design type in structural design, size, material of construction, wall thickness, or manner of construction, but does not include:
(i) A packaging which differs in surface treatment;
(ii) A rigid plastic IBC or composite IBC which differs with regard to additives used to comply with §§ 178.706(c), 178.707(c) or 178.710(c);
(iii) A packaging which differs only in its lesser external dimensions (i.e., height, width, length) provided materials of construction and material thicknesses or fabric weight remain the same;
(iv) A packaging which differs in service equipment.
(d) Design qualification testing. The packaging manufacturer shall achieve successful test results for the design qualification testing at the start of production of each new or different IBC design type. The service equipment selected for this design qualification testing shall be representative of the type of service equipment that will be fitted to any finished IBC body under the design. Application of the certification mark by the manufacturer shall constitute certification that the IBC design type passed the prescribed tests in this subpart.
(e) Periodic design requalification testing.
(1) Periodic design requalification must be conducted on each qualified IBC design type if the manufacturer is to maintain authorization for continued production. The IBC manufacturer shall achieve successful test results for the periodic design requalification at sufficient frequency to ensure each packaging produced by the manufacturer is capable of passing the design qualification tests. Design requalification tests must be conducted at least once every 12 months.
(2) Changes in the frequency of design requalification testing specified in paragraph (e)(1) of this section are authorized if approved by the Associate Administrator. These requests must be based on:
(i) Detailed quality assurance programs that assure that proposed decreases in test frequency maintain the integrity of originally tested IBC design types; and
(ii) Demonstrations that each IBC produced is capable of withstanding higher standards (e.g., increased drop height, hydrostatic pressure, wall thickness, fabric weight).
(f) Production testing and inspection.
(1) Production testing consists of the leakproofness test prescribed in § 178.813 of this subpart and must be performed on each IBC intended to contain solids discharged by pressure or intended to contain liquids. For this test:
(i) The IBC need not have its closures fitted, except that the IBC must be fitted with its primary bottom closure.
(ii) The inner receptacle of a composite IBC may be tested without the outer IBC body, provided the test results are not affected.
(2) Applicable inspection requirements in § 180.352 of this subchapter must be performed on each IBC initially after production.
(g) Test samples. The IBC manufacturer shall conduct the design qualification and periodic design requalification tests prescribed in this subpart using random samples of IBCs, according to the appropriate test section.
(h) Selective testing of IBCs. Variation of a tested IBC design type is permitted without further testing, provided selective testing demonstrates an equivalent or greater level of safety than the design type tested and which has been approved by the Associate Administrator.
(i) Approval of equivalent packagings. An IBC differing from the standards in subpart N of this part, or tested using methods other than those specified in this subpart, may be used if approved by the Associate Administrator. Such IBCs must be shown to be equally effective, and testing methods used must be equivalent.
(j) Proof of compliance. Notwithstanding the periodic design requalification testing intervals specified in paragraph (e) of this section, the Associate Administrator, or a designated representative, may at any time require demonstration of compliance by a manufacturer, through testing in accordance with this subpart, that packagings meet the requirements of this subpart. As required by the Associate Administrator, or a designated representative, the manufacturer shall either:
(1) Conduct performance tests or have tests conducted by an independent testing facility, in accordance with this subpart; or
(2) Make a sample IBC available to the Associate Administrator, or a designated representative, for testing in accordance with this subpart.
(k) Coatings. If an inner treatment or coating of an IBC is required for safety reasons, the manufacturer shall design the IBC so that the treatment or coating retains its protective properties even after withstanding the tests prescribed by this subpart.
(l) Record retention. Following each design qualification test and each periodic retest on an IBC, a test report must be prepared.
(1) The test report must be maintained at each location where the packaging is manufactured, certified, and a design qualification test or periodic retest is conducted as follows:
Responsible party Duration Person manufacturing the packaging As long as manufactured and two years thereafter. Person performing design testing Design test maintained for a single or composite packaging for six years after the test is successfully performed and for a combination packaging or packaging intended for infectious substances for seven years after the test is successfully performed. Person performing periodic retesting Performance test maintained for a single or composite packaging for one year after the test is successfully performed and for a combination packaging or packaging intended for infectious substances for two years after the test is successfully performed. (2) The test report must be made available to a user of a packaging or a representative of the Department upon request. The test report, at a minimum, must contain the following information:
(i) Name and address of test facility;
(ii) Name and address of the person certifying the IBC;
(iii) A unique test report identification;
(iv) Date of test report;
(v) Manufacturer of the IBC;
(vi) Description of the IBC design type (e.g., dimensions, materials, closures, thickness, representative service equipment, etc.);
(vii) Maximum IBC capacity;
(viii) Characteristics of test contents, including for rigid plastics and composite IBCs subject to the hydrostatic pressure test in § 178.814 of this subpart, the temperature of the water used;
(ix) Test descriptions and results (including drop heights, hydrostatic pressures, tear propagation length, etc.); and
(x) The signature of the person conducting the test, and name of the person responsible for testing.
[Amdt. 178-103, 59 FR 38074, July 26, 1994, as amended by Amdt. 178-108, 60 FR 40038, Aug. 4, 1995; 66 FR 45386, Aug. 28, 2001; 66 FR 33452, June 21, 2001; 68 FR 75758, Dec. 31, 2003; 73 FR 57008, Oct. 1, 2008; 74 FR 2269, Jan. 14, 2009; 75 FR 5397, Feb. 2, 2010; 78 FR 14715, Mar. 7, 2013; 78 FR 65487, Oct. 31, 2013; 80 FR 72929, Nov. 23, 2015; 85 FR 27901, May 11, 2020]