§ 365.2 - Definitions.  


Latest version.
  • (a) For the purpose of this part terms will have the same meaning as defined in the Public Utility Holding Company Act of 1935, as amended by the Energy Policy Act of 1992, except as provided in paragraph (b) of this section.

    (b) For the purpose of this part:

    (1) Commission means the Federal Energy Regulatory Commission; and

    (2) Receipt of an application means the date on which the Commission receives the application or an amendment allowed for good cause shown and the applicable filing fee, if any; and

    (3) Affected State commission means the State commission of each state in which a generating facility owned and/or operated by the applicant is located; each State commission regulating the retail rates of an electric utility that will purchase power from the applicant, if known at the time of application; and, each State commission regulating a retail utility that is affiliated with the applicant.