§ 250.1730 - When might BSEE approve partial structure removal or toppling in place?  


Latest version.
  • § 250.1730 When might BSEE approve partial structure removal or toppling in place?

    The Regional Supervisor may grant a departure from the requirement to remove a platform or other facility by approving partial structure removal or toppling in place for conversion to an artificial reef if you meet the following conditions:

    (a) The structure becomes part of a State artificial reef program, and the responsible State agency acquires a permit from the U.S. Army Corps of Engineers and accepts title and liability for the structure; and

    (b) You satisfy any U.S. Coast Guard (USCG) navigational requirements for the structure.