  • § 265.54 Amendment of contingency plan.

    The contingency plan must be reviewed, and immediately amended, if necessary, whenever:

    (a) Applicable regulations are revised;

    (b) The plan fails in an emergency;

    (c) The facility changes - in its design, construction, operation, maintenance, or other circumstances - in a way that materially increases the potential for fires, explosions, or releases of hazardous waste or hazardous waste constituents, or changes the response necessary in an emergency;

    (d) The list of emergency coordinators changes; or

    (e) The list of emergency equipment changes.

    [45 FR 33232, May 19, 1980, as amended at 50 FR 4514, Jan. 31, 1985]