Code of Federal Regulations (Last Updated: November 8, 2024) |
Title 30 - Mineral Resources |
Chapter II - Bureau of Safety and Environmental Enforcement, Department of the Interior |
SubChapter B - Offshore |
Part 285 - [Reserved] |
Subpart F - Plans and Information Requirements |
Construction and Operations Plan for Commercial Leases |
§ 285.620 - What is a Construction and Operations Plan (COP)?
-
The COP describes your construction, operations, and conceptual decommissioning plans under your commercial lease, including your project easement. The MMS will withhold trade secrets and commercial or financial information that is privileged or confidential from public disclosure under exemption 4 of the FOIA and in accordance with the terms of § 285.113.
(a) Your COP must describe all planned facilities that you will construct and use for your project, including onshore and support facilities and all anticipated project easements.
(b) Your COP must describe all proposed activities including your proposed construction activities, commercial operations, and conceptual decommissioning plans for all planned facilities, including onshore and support facilities.
(c) You must receive MMS approval of your COP before you can begin any of the approved activities on your lease.