  • § 585.703 What reports must I submit for project modifications and repairs?

    (a) You must verify and, in a report to us, certify that major repairs and major modifications to the project conform to accepted engineering practices.

    (1) A major repair is a corrective action involving structural members affecting the structural integrity of a portion of or all the facility.

    (2) A major modification is an alteration involving structural members affecting the structural integrity of a portion of or all the facility.

    (b) The report must also identify the location of all records pertaining to the major repairs or major modifications, as required in § 585.714(c).

    (c) BOEM may require you to use a CVA for project modifications and repairs.