Code of Federal Regulations (Last Updated: November 8, 2024) |
Title 40 - Protection of Environment |
Chapter I - Environmental Protection Agency |
SubChapter C - Air Programs |
Part 63 - National Emission Standards for Hazardous Air Pollutants for Source Categories |
Subpart RRRRR - National Emission Standards for Hazardous Air Pollutants: Taconite Iron Ore Processing |
Initial Compliance Requirements |
§ 63.9622 - What test methods and other procedures must I use to establish and demonstrate initial compliance with the operating limits?
-
§ 63.9622 What test methods and other procedures must I use to establish and demonstrate initial compliance with the operating limits?
(a) For wet scrubbers subject to performance testing in § 63.9620 and operating limits for pressure drop and scrubber water flow rate in § 63.9590(b)(1), you must establish site-specific operating limits according to the procedures in paragraphs (a)(1) through (3) of this section.
(1) Using the CPMS required in § 63.9631(b), measure and record the pressure drop and scrubber water flow rate every 15 minutes during each run of the particulate matter performance test.
(2) Calculate and record the average pressure drop and scrubber water flow rate for each individual test run. Your operating limits are established as the lowest average pressure drop and the lowest average scrubber water flow rate corresponding to any of the three test runs, except as specified in paragraph (g)(2) of this section.
(3) If a rod-deck venturi scrubber is applied to an indurating furnace to meet any particulate matter emission limit in Table table 1 to this subpart, you may establish a lower average pressure drop operating limit by using historical average pressure drop data from a certified performance test completed on or after December 18, 2002 instead of using the average pressure drop value determined during the initial performance test, as specified in paragraph (a)(2) of this section. If historical average pressure drop data are used to establish an operating limit (i.e., using data from a certified performance test conducted prior to the promulgation date of the final rule), then the average particulate matter concentration corresponding to the historical performance test must be at or below the applicable indurating furnace emission limit, as listed in Table table 1 to this subpart.
(b) On or before January 28, 2022, for affected sources that commenced construction or reconstruction on or before September 25, 2019, for dynamic wet scrubbers subject to performance testing in § 63.9620 and operating limits for scrubber water flow rate and either fan amperage or pressure drop in § 63.9590(b)(2), you must establish site-specific operating limits according to the procedures in paragraphs (b)(1) and (2) of this section. After January 28, 2022, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, for dynamic wet scrubbers subject to performance testing in § 63.9620 and operating limits for scrubber water flow rate and fan amperage in § 63.9590(b)(2), you must establish site-specific operating limits according to the procedures in paragraphs (b)(1) and (2) of this section.
(1) On or before January 28, 2022, for affected sources that commenced construction or reconstruction on or before September 25, 2019, using the CPMS required in § 63.9631(b), measure and record the scrubber water flow rate and either the fan amperage or pressure drop every 15 minutes during each run of the particulate matter performance test. After January 28, 2022, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, using the CPMS required in § 63.9631(b), measure and record the scrubber water flow rate and the fan amperage every 15 minutes during each run of the particulate matter performance test.
(2) On or before January 28, 2022, for affected sources that commenced construction or reconstruction on or before September 25, 2019, calculate and record the average scrubber water flow rate and either the average fan amperage or the average pressure drop for each individual test run. Your operating limits are established as the lowest average scrubber water flow rate and either the lowest average fan amperage or pressure drop value corresponding to any of the three test runs. After January 28, 2022, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, calculate and record the average scrubber water flow rate and the average fan amperage for each individual test run. Your operating limits are established as the lowest average scrubber water flow rate and the lowest average fan amperage value corresponding to any of the three test runs, except as specified in paragraph (g)(2) of this section.
(c) For a dry electrostatic precipitator ESP subject to performance testing in § 63.9620 and operating limits in § 63.9590(b)(3), you must establish a site-specific operating limit according to the procedures in paragraphs (c)(1) or (2) of this section.
(1) If the operating limit for your dry electrostatic precipitator ESP is a 6-minute average opacity of emissions value, then you must follow the requirements in paragraphs (c)(1)(i) through (iii) of this section.
(i) Using the continuous opacity monitoring system (COMS) required in § 63.9631(d)(1), measure and record the opacity of emissions from each control device stack during the particulate matter performance test.
(ii) Compute and record the 6-minute opacity averages from 24 or more data points equally spaced over each 6-minute period (e.g., at 15-second intervals) during the test runs.
(iii) Using the opacity measurements from a performance test that meets the emission limit, determine the opacity value corresponding to the 99 percent upper confidence level of a normal distribution of the 6-minute opacity averages.
(2) If the operating limit for your dry electrostatic precipitator ESP is the daily average secondary voltage and daily average secondary current for each field, then you must follow the requirements in paragraphs (c)(2)(i) and (ii) of this section.
(i) Using the CPMS required in § 63.9631(d)(2), measure and record the secondary voltage and secondary current for each dry electrostatic precipitator ESP field every 15 minutes during each run of the particulate matter performance test.
(ii) Calculate and record the average secondary voltage and secondary current for each dry electrostatic precipitator ESP field for each individual test run. Your operating limits are established as the lowest average secondary voltage and secondary current value for each dry electrostatic precipitator ESP field corresponding to any of the three test runs.
(d) For a wet electrostatic precipitator ESP subject to performance testing in § 63.9620 and operating limit in § 63.9590(b)(4), you must establish a site-specific operating limit according to the procedures in paragraphs (d)(1) and (2) of this section.
(1) Using the CPMS required in § 63.9631(e), measure and record the parametric values in paragraphs (d)(1)(i) through (iii) of this section for each wet electrostatic precipitator ESP field every 15 minutes during each run of the particulate matter performance test.
(i) Secondary voltage;
(ii) Water flow rate; and
(iii) Stack outlet temperature.
(2) For each individual test run, calculate and record the average value for each operating parameter in paragraphs (d)(1)(i) through (iii) of this section for each wet electrostatic precipitator ESP field. Your operating limits are established as the lowest average value for each operating parameter of secondary voltage and water flow rate corresponding to any of the three test runs, and the highest average value for each stack outlet temperature corresponding to any of the three test runs.
(e) If you use an air pollution control device other than a wet scrubber, dynamic wet scrubber, dry electrostatic precipitatorESP, wet electrostatic precipitatorESP, or baghouse, and it is subject to performance testing in § 63.9620, you must submit a site-specific monitoring plan in accordance with § 63.9631(f). The site-specific monitoring plan must include the site-specific procedures for demonstrating initial and continuous compliance with the corresponding operating limits.
(f) You may change the operating limits for any air pollution control device as long as you meet the requirements in paragraphs (f)(1) through (3) of this section.
(1) Submit a written notification to the Administrator of your request to conduct a new performance test to revise the operating limit.
(2) Conduct a performance test to demonstrate compliance with the applicable emission limitation in Table table 1 to this subpart.
(3) Establish revised operating limits according to the applicable procedures in paragraphs (a) through (e) of this section.
(g) For wet scrubbers and wet ESPs subject to performance testing in § 63.9620(l) and operating limits for scrubber water flow rate and pH in § 63.9590(b)(5), you must establish site-specific operating limits according to the procedures in paragraphs (g)(1) and (2) of this section.
(1) Using the CPMS required in § 63.9631(b), measure and record the scrubber water flow rate and pH of the scrubber water effluent every 15 minutes during each run of the performance test for hydrogen chloride and hydrogen fluoride.
(2) Calculate and record the average scrubber water flow rate and average pH of the scrubber water effluent for each individual test run. Your operating limit must be established as the average scrubber water flow rate and average pH of the scrubber water of the three test runs. If a higher average flow rate is measured during the most recent PM performance test, the operating limit for the daily average scrubber water flow rate is the average scrubber water flow rate measured during the most recent PM performance test. If a higher average flow rate is measured during the most recent HCl and HF performance test, the operating limit for the daily average scrubber water flow rate is the average scrubber water flow rate measured during the most recent HCl and HF performance test.
(h) For ACI systems subject to performance testing in § 63.9620(k)(1) and operating limits for activated carbon sorbent injection rate and carrier gas flow rate in § 63.9590(b)(6), you must establish site-specific operating limits according to the procedures in paragraphs (h)(1) and (2) of this section.
(1) Using the CPMS required in § 63.9631(b), measure and record the activated carbon injection rate and carrier gas flow rate every 15 minutes during each run of the performance test for mercury.
(2) Calculate and record the average activated carbon injection rate and carrier gas flow rate for each individual test run. Your operating limit must be established as the highest activated carbon injection rate and carrier gas flow rate of the three test runs.
(i) For DSI systems subject to performance testing in § 63.9620(l) and operating limits for sorbent injection rate and carrier gas flow rate in § 63.9590(b)(7), you must establish site-specific operating limits according to the procedures in paragraphs (i)(1) and (2) of this section.
(1) Using the CPMS required in § 63.9631(b), measure and record the sorbent injection rate and carrier gas flow rate every 15 minutes during each run of the performance test for hydrogen chloride and hydrogen fluoride.
(2) Calculate and record the average sorbent injection rate and carrier gas flow rate for each individual test run. Your operating limit must be established as the highest average sorbent injection rate and carrier gas flow rate of the three test runs.
[68 FR 61888, Oct. 30, 2003, as amended at 85 FR 45493, July 28, 2020; 89 FR 16428, Mar. 6, 2024]