§ 63.9634 - How do I demonstrate continuous compliance with the emission limitations that apply to me?  


Latest version.
  • § 63.9634 How do I demonstrate continuous compliance with the emission limitations that apply to me?

    (a) For each affected source subject to an emission limit in Table table 1 to this subpart, you must demonstrate continuous compliance by meeting the requirements in paragraphs (b) through (fh) of this section.

    (b) For ore crushing and handling affected sources and finished pellet handling affected sources, you must demonstrate continuous compliance by meeting the requirements in paragraphs (b)(1) through (3) of this section.

    (1) The flow-weighted mean concentration of particulate matter for all ore crushing and handling emission units and for all finished pellet handling emission units must be maintained at or below the emission limits in Table 1 to this subpart.

    (2) You must conduct subsequent performance tests for emission units in the ore crushing and handling and finished pellet handling affected sources following the schedule in your title V permit. If a title V permit has not been issued, you must conduct subsequent performance tests according to a testing plan approved by the Administrator or delegated authority.

    (3) For ore crushing and handling and finished pellet handling emission units not selected for initial performance testing and defined within a group of similar emission units in accordance with § 63.9620(e), the site-specific operating limits established for the emission unit selected as representative of a group of similar emission units will be used as the operating limit for each emission unit within the group. The operating limit established for the representative unit must be met by each emission unit within the group.

    (c) For ore dryers and indurating furnaces, you must demonstrate continuous compliance by meeting the requirements in paragraphs (c)(1) and (2) of this section.

    (1) The flow-weighted mean concentration of particulate matter for all stacks from the ore dryer or indurating furnace must be maintained at or below the emission limits in Table 1 to this subpart.

    (2) For ore dryers, you must conduct subsequent performance tests following the schedule in your title V permit. For indurating furnaces, you must conduct subsequent performance tests following the schedule in your title V permit, but no less frequent than twice per 5-year permit term. If a title V permit has not been issued, you must conduct subsequent performance tests according to a testing plan approved by the Administrator or delegated authority.

    (d) On or before January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, for each baghouse applied to meet any particulate emission limit in Table 1 to this subpart, you must demonstrate continuous compliance by completing the requirements in paragraphs (d)(1) and (2) of this section. After January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, for each baghouse applied to meet any particulate emission limit in Table 1 to this subpart, you must demonstrate continuous compliance by completing the requirements in paragraphs (d)(1) through (3) of this section.

    (1) Maintaining records of the time you initiated corrective action in the event of a bag leak detection system alarm, the corrective action(s) taken, and the date on which corrective action was completed.

    (2) Inspecting and maintaining each baghouse according to the requirements in § 63.9631(a) and recording all information needed to document conformance with the requirements in § 63.9631(a). If you increase or decrease the sensitivity of the bag leak detection system beyond the limits specified in your site-specific monitoring plan, you must include a copy of the required written certification by a responsible official in the next semiannual compliance report.

    (3) Each bag leak detection system must be operated and maintained such that the alarm does not sound more than 5 percent of the operating time during a 6-month period. Calculate the alarm time as specified in paragraphs (d)(3)(i) through (iii) of this section.

    (i) If inspection of the fabric filter demonstrates that no corrective action is required, no alarm time is counted.

    (ii) If corrective action is required, each alarm time (i.e., time that the alarm sounds) is counted as a minimum of 1 hour.

    (iii) If it takes longer than 1 hour to initiate corrective action, each alarm time is counted as the actual amount of time taken to initiate corrective action.

    (e) Except as provided in paragraph (f) of this section, for each wet scrubber subject to the operating limits for pressure drop and scrubber water flow rate in § 63.9590(b)(1), you must demonstrate continuous compliance by completing the requirements of paragraphs (e)(1) through (4) of this section.

    (1) Maintaining the daily average pressure drop and daily average scrubber water flow rate at or above the minimum levels established during the initial or subsequent performance test.

    (2) Operating and maintaining each wet scrubber CPMS according to § 63.9632(b) and recording all information needed to document conformance with these requirements.

    (3) Collecting and reducing monitoring data for pressure drop and scrubber water flow rate according to § 63.9632(c) and recording all information needed to document conformance with these requirements.

    (4) If the daily average pressure drop or daily average scrubber water flow rate is below the operating limits established for a corresponding emission unit or group of similar emission units, you must then follow the corrective action procedures in paragraph (jl) of this section.

    (f) On or before January 28, 2022, for affected sources that commenced construction or reconstruction on or before September 25, 2019, for each dynamic wet scrubber subject to the operating limits for scrubber water flow rate and either the fan amperage or pressure drop in § 63.9590(b)(2), you must demonstrate continuous compliance by completing the requirements of paragraphs (f)(1) through (4) of this section. After January 28, 2022, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, for each dynamic wet scrubber subject to the operating limits for scrubber water flow rate and the fan amperage in § 63.9590(b)(2), you must demonstrate continuous compliance by completing the requirements of paragraphs (f)(1) through (4) of this section.

    (1) On or before January 28, 2022, for affected sources that commenced construction or reconstruction on or before September 25, 2019, maintaining the daily average scrubber water flow rate and either the daily average fan amperage or the daily average pressure drop at or above the minimum levels established during the initial or subsequent performance test. After January 28, 2022, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, maintaining the daily average scrubber water flow rate and the daily average fan amperage at or above the minimum levels established during the initial or subsequent performance test.

    (2) Operating and maintaining each dynamic wet scrubber CPMS according to § 63.9632(b) and recording all information needed to document conformance with these requirements.

    (3) On or before January 28, 2022, for affected sources that commenced construction or reconstruction on or before September 25, 2019, collecting and reducing monitoring data for scrubber water flow rate and either fan amperage or pressure drop according to § 63.9632(c) and recording all information needed to document conformance with the requirements in § 63.9632(c). After January 28, 2022, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, collecting and reducing monitoring data for scrubber water flow rate and fan amperage according to § 63.9632(c) and recording all information needed to document conformance with the requirements in § 63.9632(c).

    (4) On or before January 28, 2022, for affected sources that commenced construction or reconstruction on or before September 25, 2019, if the daily average scrubber water flow rate, daily average fan amperage, or daily average pressure drop is below the operating limits established for a corresponding emission unit or group of similar emission units, you must then follow the corrective action procedures in paragraph (jl) of this section. After January 28, 2022, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, if the daily average scrubber water flow rate or daily average fan amperage, is below the operating limits established for a corresponding emission unit or group of similar emission units, you must then follow the corrective action procedures in paragraph (jl) of this section.

    (g) For each dry electrostatic precipitator ESP subject to operating limits in § 63.9590(b)(3), you must demonstrate continuous compliance by completing the requirements of paragraph (g)(1) or (2) of this section.

    (1) If the operating limit for your dry electrostatic precipitator ESP is a 6-minute average opacity of emissions value, then you must follow the requirements in paragraphs (g)(1)(i) through (iii) of this section.

    (i) Maintaining the 6-minute average opacity of emissions at or below the maximum level established during the initial or subsequent performance test.

    (ii) Operating and maintaining each COMS and reducing the COMS data according to § 63.9632(f).

    (iii) If the 6-minute average opacity of emissions is above the operating limits established for a corresponding emission unit, you must then follow the corrective action procedures in paragraph (jl) of this section.

    (2) If the operating limit for your dry electrostatic precipitator ESP is the daily average secondary voltage and daily average secondary current for each field, then you must follow the requirements in paragraphs (g)(2)(i) through (iv) of this section.

    (i) Maintaining the daily average secondary voltage or daily average secondary current for each field at or above the minimum levels established during the initial or subsequent performance test.

    (ii) Operating and maintaining each dry electrostatic precipitator ESP CPMS according to § 63.9632(b) and recording all information needed to document conformance with these requirements.

    (iii) Collecting and reducing monitoring data for secondary voltage or secondary current for each field according to § 63.9632(c) and recording all information needed to document conformance with these requirements.

    (iv) If the daily average secondary voltage or daily average secondary current for each field is below the operating limits established for a corresponding emission unit, you must then follow the corrective action procedures in paragraph (jl) of this section.

    (h) For each wet electrostatic precipitator ESP subject to the operating limits for secondary voltage, stack outlet temperature, and water flow rate in § 63.9590(b)(4), you must demonstrate continuous compliance by completing the requirements of paragraphs (h)(1) through (4) of this section.

    (1) Maintaining the daily average secondary voltage and daily average scrubber water flow rate for each field at or above the minimum levels established during the initial or subsequent performance test. Maintaining the daily average stack outlet temperature at or below the maximum levels established during the initial or subsequent performance test.

    (2) Operating and maintaining each wet electrostatic precipitator ESP CPMS according to § 63.9632(b) and recording all information needed to document conformance with these requirements.

    (3) Collecting and reducing monitoring data for secondary voltage, stack outlet temperature, and water flow rate according to § 63.9632(c) and recording all information needed to document conformance with these requirements.

    (4) If the daily average secondary voltage, stack outlet temperature, or water flow rate does not meet the operating limits established for a corresponding emission unit, you must then follow the corrective action procedures in paragraph (l) of this section.

    (i) For each affected indurating furnace subject to a hydrogen chloride and hydrogen fluoride emission limit in table 3 to this subpart, you must demonstrate continuous compliance by meeting the requirements in paragraphs (i)(1) and (2) of this section.

    (1) For each wet scrubber and wet ESP subject to the operating limits for scrubber water flow rate and pH in § 63.9590(b)(5), you must demonstrate continuous compliance by completing the requirements of paragraphs (i)(1)(i) through (iv) of this section.

    (i) Maintaining the daily average scrubber water flow rate and daily average pH of the scrubber water effluent at or above the minimum level established during the most recent performance test. If a higher average flow rate is measured during the last PM performance test, the operating limit for daily average scrubber water flow rate is the highest average scrubber water flow rate measured during the last PM performance test.

    (ii) Operating and maintaining each of the CPMS used to measure scrubber water flow rate and pH according to § 63.9632(g) and recording all information needed to document conformance with these requirements.

    (iii) Collecting and reducing monitoring data for scrubber water flow rate and pH according to § 63.9632(c) and recording all information needed to document conformance with these requirements.

    (iv) If the daily average scrubber water flow rate or daily average pH is below the operating limits established for control device, you must follow the corrective action procedures in paragraph (l) of this section.

    (2) For each DSI subject to the operating limits for sorbent injection rate and carrier gas flow rate in § 63.9590(b)(7), you must demonstrate continuous compliance by completing the requirements of paragraphs (i)(2)(i) through (iv) of this section.

    (i) Maintain the daily average sorbent injection rate and carrier gas flow rate at or above the minimum level established during the most recent performance test.

    (ii) Operate and maintain each CPMS used to measure the sorbent injection rate according to § 63.9632(h) and the carrier gas flow rate according to § 63.9632(i) and recording all information needed to document compliance with these requirements.

    (iii) Collect and reduce monitoring data for the sorbent injection rate and carrier gas flow rate according to § 63.9632(c) and recording all information needed to document compliance with these requirements.

    (iv) If the daily average the sorbent injection rate or carrier gas flow rate is below the operating limit established for the control device, you must follow the corrective action procedures in paragraph (l) of this section.

    (j) For each affected indurating furnace using ACI to comply with the mercury emission limit in table 2 to this subpart, you must demonstrate continuous compliance by meeting the requirements of paragraphs (j)(1) or (2) of this section.

    (1) If you use CEMS to demonstrate compliance, you must comply with the requirements in paragraphs (j)(1)(i) and (ii) of this section.

    (i) You must operate a mercury CEMS in accordance with performance specification 12A at 40 CFR part 60, appendix B; these monitoring systems must be quality assured according to procedure 5 of 40 CFR 60, appendix F. You must demonstrate compliance with the mercury emissions limit using a 30-day rolling average of these 1-hour mercury concentrations or mass emissions rates, including CEMS data during startup and shutdown as defined in this subpart, calculated using equation 19–19 in section 12.4.1 of EPA Reference Method 19 at 40 CFR part 60, appendix A–7 of this part.

    (ii) Owners or operators using a mercury CEMS to determine mass emission rate must install, operate, calibrate and maintain an instrument for continuously measuring and recording the mercury mass emissions rate to the atmosphere according to the requirements of performance specification 6 at 40 CFR part 60, appendix B and conducting an annual relative accuracy test of the continuous emission rate monitoring system according to section 8.2 of performance specification 6.

    (2) If you do not use CEMS to demonstrate compliance, you must demonstrate continuous compliance by meeting the requirements of paragraphs (j)(2)(i) through (iv) of this section.

    (i) Maintain the daily average activated carbon injection rate and carrier gas flow rate at or above the minimum level established during the most recent performance test.

    (ii) Operate and maintain each CPMS used to measure the activated carbon injection rate according to § 63.9632(h) and the carrier gas flow rate according to § 63.9632(i), and record all information needed to document compliance with these requirements.

    (iii) Collect and reduce monitoring data for the activated carbon injection rate and carrier gas flow rate according to § 63.9632(c) and record all information needed to document conformance with these requirements.

    (iv) If the daily average of the activated carbon injection rate or carrier gas flow rate is below the operating limit established for the control device, you must follow the corrective action procedures in paragraph (l) of this section.

    (k) If you use an air pollution control device other than a wet scrubber, dynamic wet scrubber, dry

    electrostatic precipitator

    ESP, wet

    electrostatic precipitator,

    ESP, DSI, ACI, or baghouse, you must submit a site-specific monitoring plan in accordance with § 63.9631(f). The site-specific monitoring plan must include the site-specific procedures for demonstrating initial and continuous compliance with the corresponding operating limits.

    (

    j

    l) If the daily average operating parameter value for an emission unit or group of similar emission units does not meet the corresponding established operating limit, you must then follow the procedures in paragraphs (

    j

    l)(1) through (4) of this section.

    (1) You must initiate and complete initial corrective action within 10 calendar days and demonstrate that the initial corrective action was successful. During any period of corrective action, you must continue to monitor, and record all required operating parameters for equipment that remains in operation. After the initial corrective action, if the daily average operating parameter value for the emission unit or group of similar emission units meets the operating limit established for the corresponding unit or group, then the corrective action was successful and the emission unit or group of similar emission units is in compliance with the established operating limits.

    (2) If the initial corrective action required in paragraph (

    j

    l)(1) of this section was not successful, then you must complete additional corrective action within 10 calendar days and demonstrate that the subsequent corrective action was successful. During any period of corrective action, you must continue to monitor, and record all required operating parameters for equipment that remains in operation. If the daily average operating parameter value for the emission unit or group of similar emission units meets the operating limit established for the corresponding unit or group, then the corrective action was successful, and the emission unit or group of similar emission units is in compliance with the established operating limits.

    (3) If the second attempt at corrective action required in paragraph (

    j

    l)(2) of this section was not successful, then you must repeat the procedures of paragraph (

    j

    l)(2) of this section until the corrective action is successful. If the third attempt at corrective action is unsuccessful, you must conduct another performance test in accordance with the procedures in § 63.9622(f) and report to the Administrator as a deviation the third unsuccessful attempt at corrective action.

    (4) After the third unsuccessful attempt at corrective action, you must submit to the Administrator the written report required in paragraph (

    j

    l)(3) of this section within 5 calendar days after the third unsuccessful attempt at corrective action. This report must notify the Administrator that a deviation has occurred and document the types of corrective measures taken to address the problem that resulted in the deviation of established operating parameters and the resulting operating limits.

    (m) If you elect to comply with the mercury limit in table 2 to this subpart using emissions averaging in accordance with an implementation plan approved under the provisions in § 63.9623(d), you must comply with the requirements in paragraphs (m)(1) through (5) of this section.

    (1) For furnaces included in the emissions averaging group that do not use mercury CEMS, you must comply with the requirements in paragraph (m)(1)(i) or (ii) as applicable.

    (i) For furnaces equipped with ACI systems, you must comply with the requirements in paragraph (j) of this section.

    (ii) For furnaces equipped with a mercury control device or method other than ACI, you must comply with your site-specific monitoring plan in accordance with the requirements in paragraph (k) of this section.

    (2) For furnaces included in the emissions averaging group that use mercury CEMS, you must comply with the requirements in paragraph (i)(1) of this section.

    (3) Calculate the monthly production-weighted average emission rate using either the mercury CEMS data or mercury emission rate determined during the last performance test and the actual taconite pellet production data for each furnace included in the emissions averaging option, as shown in Equation 6 of this section.

    Where:

    Eg = Monthly production-weighted average mercury emission rate for month “g” for the group of indurating furnaces, lb/LT of pellets produced,

    Ef = Average mercury emission rate for furnace “f”, as determined using either mercury CEMS data or the emission rate determined during the last compliance stack test and calculated using Equation 5 of § 63.9621(d)(7)(i), lb/LT of pellets produced,

    Pf = Total monthly production of finished taconite pellets for furnace “f”, in LT, and

    n = Number of furnaces in the averaging group.

    (4) Until 12 monthly weighted average emission rates have been accumulated, the monthly weighted average emissions rate, calculated as shown in paragraph (m)(3) of this section, must not exceed the mercury emission limit in table 3 of this subpart in any calendar month.

    (5) After 12 monthly weighted average emission rates have been accumulated, for each subsequent calendar month, you must use Equation 7 of this section to calculate the 12-month rolling average of the monthly weighted average emission rates for the current month and the previous 11 months. The 12-month rolling weighted average emissions rate for the furnaces included in the group must not exceed the mercury emission limit in table 3 of this subpart.

    Where:

    Eavg = 12-month rolling average emission rate, lb/LT.

    Ei = Monthly weighted average for month “i” calculated as shown in Equation 6 of this section.

    (n) You may elect to demonstrate continuous compliance with the mercury limit in table 2 to this subpart by adjusting the activated carbon injection rate based on the taconite pellet production rate. You must comply with the requirements in paragraphs (n)(1) through (7) of this section.

    (1) Measure the activated carbon injection and mercury emissions rate at a minimum of three different production levels corresponding to the maximum, minimum and median finished taconite pellet production rates, using the methods specified in § 63.9620(k).

    (2) Develop a correlation curve by plotting the production rate and corresponding carbon injection rate for the maximum, median and minimum production rates. Use only data where the mercury emission rate is below the applicable mercury emissions standard in table 2 to this subpart. Plot the production rates as the independent (or x) variable and the activated carbon injection rate as the dependent (or y) variable for each pellet production rate. Construct the graph by drawing straight line segments between each point plotted.

    (3) You must develop and submit to the applicable regulatory authority for review and approval, an implementation plan no later than 180 days before the date you intend to demonstrate compliance by adjusting the activated carbon injection rate based on the taconite pellet production. You must include the information listed in paragraphs (n)(3)(i) through (iv) of this section in your implementation plan.

    (i) Identification of the indurating furnace, including the typical maximum and minimum taconite pellet production rate, mercury control technology installed, and types of fuel(s) that will be burned.

    (ii) The mercury emissions and activated carbon injection rates at maximum, median and minimum taconite pellet production rates, and the methods used to measure the mercury emissions, activated carbon injection rate and taconite pellet production.

    (iii) The correlation curve developed in paragraph (n)(2) of this section.

    (iv) The date on which you are requesting to commence adjusting the activated carbon rate based on the taconite production rate.

    (4) Install, calibrate, maintain, and operate a CPMS to monitor and record the activated carbon injection rate and taconite pellet production rate.

    (5) Maintain the carbon injection rate at or above the rate established by the correlation curve corresponding to the taconite pellet production rate. If the taconite pellet production rate drops below the minimum rate established in paragraph (n)(3) of this section, you must maintain the activated carbon injection rate at or above the rate established for the minimum taconite pellet production rate.

    (6) Keep records of the activated carbon injection rate and taconite pellet production rate for each hour of operation in order to demonstrate that the activated carbon injection rate remains in compliance with paragraph (n)(5) of this section.

    (7) Establish a new correlation curve at least twice per 5-year permit term.

    [68 FR 61888, Oct. 30, 2003, as amended at 85 FR 45496, July 28, 2020; 89 FR 16432, Mar. 6, 2024]