§ 852.236-79 - Contractor production report.
Latest version.
-
852.236-79 Contractor production report.
Production Report.
As prescribed in 836.573, insert the following clause:
Contractor Production Report (APR 2019)
(a) The Contractor shall furnish to the resident engineer, for each workday, a consolidated report for the preceding workday. Reporting shall begin from date of mobilization until the date of final acceptance except for authorized holidays. VA Form 10101, Contractor Production Report, or a Contractor generated form containing the same type of information shall be signed, dated and submitted by the Contractor superintendent.
(b) Each report shall include and specifically identify at least one safety topic germane to the jobsite that day.
(End of clause)