Code of Federal Regulations (Last Updated: November 8, 2024) |
Title 49 - Transportation |
Subtitle B - Other Regulations Relating to Transportation |
Chapter VI - Federal Transit Administration, Department of Transportation |
Part 659 - Rail Fixed Guideway Systems; State Safety Oversight |
Subpart C - Role of the State Oversight Agency |
§ 659.25 - Annual review of system safety program plan and system security plan.
-
§ 659.25 Annual review of system safety program plan and system security plan.
(a) The oversight agency shall require the rail transit agency to conduct an annual review of its system safety program plan and system security plan.
(b) In the event the rail transit agency's system safety program plan is modified, the rail transit agency must submit the modified plan and any subsequently modified procedures to the oversight agency for review and approval. After the plan is approved, the oversight agency must issue a formal letter of approval to the rail transit agency.
(c) In the event the rail transit agency's system security plan is modified, the rail transit agency must make the modified system security plan and accompanying procedures available to the oversight agency for review, consistent with requirements specified in § 659.23(e) of this part. After the plan is approved, the oversight agency shall issue a formal letter of approval to the rail transit agency.