§ 4280.124 - Servicing RES and EEI grants.  


Latest version.
  • § 4280.124 Construction planning and performing development.

    (a) General. The following requirements are applicable to all procurement methods specified in paragraph (f)

    Servicing RES and EEI grants.

    The Agency will service RES and EEI grants in accordance with the requirements specified in Departmental Regulations; 7 CFR part 3; 7 CFR 1951 Subparts E and O; the Financial Assistance Agreement; and paragraphs (a) through (k) of this section.

    (

    1) Maximum open and free competition. All procurement transactions, regardless of procurement method and dollar value, must be conducted in a manner that provides maximum open and free competition. Procurement procedures must not restrict or eliminate competition. Competitive restriction examples include, but are not limited to, the following: Placing unreasonable requirements on firms in order for them to qualify to do business; noncompetitive practices between firms; organizational conflicts of interest; and unnecessary experience or excessive bonding requirements. In specifying material(s), the grantee and its consultant will consider all materials normally suitable for the project commensurate with sound engineering practices and project requirements. The Agency will consider any recommendation made by the grantee's consultant concerning the technical design and choice of materials to be used for such a project. If the Agency determines that a design or material, other than those that were recommended, should be considered by including them in the procurement process as an acceptable design or material in the project, the Agency will provide such Applicant or grantee with a comprehensive justification for such a determination. The justification will be documented in writing.

    (2) Equal employment opportunity. For all construction contracts and grants in excess of $10,000, the contractor must comply with Executive Order 11246, as amended by Executive Order 11375 and Executive Order 13672, and as supplemented by applicable Department of Labor regulations (41 CFR part 60). The Applicant, or the lender and borrower, as applicable, is responsible for ensuring that the contractor complies with these requirements.

    (3) Surety. Any contract exceeding $100,000 for procurement will require surety, except as provided for in paragraph (a)(3)(v) of this section.

    (i) Surety covering both performance and payment will be required. The United States, acting through the Agency, will be named as co-obligee on all surety unless prohibited by State or Tribal law. Surety may be provided as specified in paragraphs (a)(3)(i)(A) or (B) of this section.

    (A) Surety in the amount of 100 percent of the contract cost may be provided using either:

    (1) A bank letter of credit; or

    (2) Performance bonds and payment bonds. Companies providing performance bonds and payment bonds must hold a certificate of authority as an acceptable surety on Federal bonds as listed in Treasury Circular 570 as amended and be legally doing business in the State where the project is located.

    (B) Cash deposit in escrow of at least 50 percent of the contract amount. The cash deposit cannot be from funds awarded under this subpart.

    (ii) The surety will normally be in the form of performance bonds and payment bonds; however, when other methods of surety are necessary, bid documents must contain provisions for such alternative types of surety. The use of surety other than performance bonds and payment bonds requires concurrence by the Agency after submission of a justification to the Agency together with the proposed form of escrow agreement or letter of credit.

    (iii) For contracts of lesser amounts, the grantee may require surety.

    (iv) When surety is not provided, contractors must furnish evidence of payment in full for all materials, labor, and any other items procured under the contract in an Agency-approved form.

    (v) Applicants may request exceptions to surety for any of the situations identified in paragraphs (a)(3)(v)(A) through (D) of this section. Applicants must submit a written request to the Agency.

    (A) Small acquisition and construction procedures as specified in § 4280.118(c) and (d) or § 4280.119(c) and (d) as applicable are used.

    (B) The proposed project is for equipment purchase and installation only and the contract costs for the equipment purchase and installation are $200,000 or less.

    (C) The proposed project is for equipment purchase and installation only and the contract costs for the equipment purchase and installation are more than $200,000 and the following requirements can be met:

    (1) The project involves two or fewer subcontractors; and

    (2) The equipment manufacturer or provider must act as the general contractor.

    (D) Other construction projects that have only one contractor performing work.

    (4) Grantees accomplishing work. In some instances, grantees may wish to perform a part of the work themselves. Grantees may accomplish construction by using their own personnel and equipment, provided the grantees possess the necessary skills, abilities, and resources to perform the work and there is not a negative impact to their business operation. For a grantee to provide a portion of the work, with the remainder to be completed by a contractor:

    (i) A clear understanding of the division of work must be established and delineated in the contract;

    (ii) Grantees are not eligible for payment for their own work as it is not an Eligible Project Cost;

    (iii) Warranty requirements applicable to the technology must cover the grantee's work; and

    (iv) Inspection and acceptance of the grantee's work must be completed by either:

    (A) An Inspector that will:

    (1) Inspect, as applicable, and accept construction; and

    (2) Furnish inspection reports; or

    (B) A licensed engineer that will:

    (1) Prepare design drawings and specifications;

    (2) Inspect, as applicable, and accept construction; and

    (3) Furnish inspection reports.

    (b) Forms used. Technical service and procurement documents must be approved by the Agency and may be used only if they are customarily used in the area and protect the interest of the Applicant and the Government with respect to compliance with items such as the drawings, specifications, payments for work, inspections, completion, nondiscrimination in construction work and acceptance of the work. The Agency will not become a party to a construction contract or incur any liability under it. No contract will become effective until concurred in writing by the Agency. Such concurrence statement must be attached to and made a part of the contract.

    (c) Technical services. Unless the requirements of paragraph (c)(4) of this section can be met, all RES and EEI projects with Total Project Costs greater than $400,000 require:

    (1) The design, installation monitoring, testing prior to commercial operation, and project completion certification be completed by a licensed professional engineer (PE) or team of licensed PEs. Licensed PEs may be “in-house” PEs or contracted PEs.

    (2) Any contract for design services must be subject to Agency concurrence.

    (3) Engineers must be licensed in the State where the project is to be constructed.

    (4) The Agency may grant an exception to the requirements of paragraphs (c)(1) through (3) of this section if the following requirements are met:

    (i) State or Tribal law does not require the use of a licensed PE; and

    (ii) The project is not complex, as determined by the Agency, and can be completed to meet the requirements of this program without the services of a licensed PE.

    (d) Design policies. Final plans and specifications must be reviewed by the Agency and approved prior to the start of construction. Facilities funded by the Agency must meet the following design requirements, as applicable:

    (1) Environmental requirements. Actions taken under this subpart must comply with the environmental review requirements in accordance with 7 CFR part 1970. Project planning and design must not only be responsive to the grantee's needs but must consider the environmental consequences of the proposed project. Project design must incorporate and integrate, where practicable, mitigation measures that avoid or minimize adverse environmental impacts. Environmental reviews serve as a means of assessing environmental impacts of project proposals, rather than justifying decisions already made. Applicants may not take any action on a project proposal that will have an adverse environmental impact or limit the choice of reasonable project alternatives being reviewed prior to the completion of the Agency's environmental review. If such actions are taken, the Agency has the right to withdraw and discontinue processing the application.

    (2) Architectural barriers. All facilities intended for or accessible to the public or in which physically handicapped persons may be employed must be developed in compliance with the Architectural Barriers Act of 1968 (42 U.S.C. 4151 et seq.) as implemented by 41 CFR 101-19.6, section 504 of the Rehabilitation Act of 1973 (42 U.S.C. 1474 et seq.) as implemented by 7 CFR parts 15 and 15b, and Titles II and III of the Americans with Disabilities Act of 1990 (42 U.S.C. 12101 et seq.).

    (3) Energy/environment. Project design shall consider cost effective energy-efficient and environmentally-sound products and services.

    (4) Seismic safety. All new structures, fully or partially enclosed, used or intended for sheltering persons or property will be designed with appropriate seismic safety provisions in compliance with the Earthquake Hazards Reduction Act of 1977 (42 U.S.C. 7701 et seq.), and EO 12699, Seismic Safety of Federal and Federally Assisted or Regulated New Building Construction. Designs of components essential for system operation and substantial rehabilitation of structures that are used for sheltering persons or property shall incorporate seismic safety provisions to the extent practicable as specified in 7 CFR part 1792, subpart C.

    (e) Contract methods. This paragraph identifies the three types of contract methods that can be used for projects funded under this subpart. The procurement methods, which are applicable to each of these contract methods, are specified in paragraph (f) of this section.

    (1) Traditional method or design-bid-build. The services of the consulting engineer or architect and the general construction contractor must be procured in accordance with the following paragraphs.

    (i) Solicitation of offers. Solicitation of offers must:

    (A) Incorporate a clear and accurate description of the technical requirements for the material, product, or service to be procured. The description must not, in competitive procurements, contain features that unduly restrict competition. The description may include a statement of the qualitative nature of the material, product or service to be procured, and when necessary will set forth those minimum essential characteristics and standards to which it must conform if it is to satisfy its intended use. When it is impractical or uneconomical to make a clear and accurate description of the technical requirements, a “brand name or equal” description may be used to define the performance or other salient requirements of a procurement. The specific features of the named brands which must be met by offerors must be clearly stated.

    (B) Clearly specify all requirements which offerors must fulfill and all other factors to be used in evaluating bids or proposals.

    (ii) Contract pricing. Cost plus a percentage of cost method of contracting must not be used.

    (iii) Unacceptable bidders. The following will not be allowed to bid on, or negotiate for, a contract or subcontract related to the construction of the project:

    (A) An engineer or architect as an individual or entity who has prepared plans and specifications or who will be responsible for monitoring the construction;

    (B) Any entity in which the grantee's architect or engineer is an officer, employee, or holds or controls a substantial interest in the grantee;

    (C) The grantee's governing body officers, employees, or agents;

    (D) Any member of the grantee's Immediate Family or partners in paragraphs (e)(1)(iii)(A), (B), or (C) of this section; or

    (E) An entity which employs, or is about to employ, any person in paragraph (e)(1)(iii)(A), (B), (C), or (D) of this section.

    (iv) Contract award. Contracts must be made only with responsible parties possessing the potential ability to perform successfully under the terms and conditions of a proposed procurement. Consideration must include, but not be limited to, matters such as integrity, record of past performance, financial and technical resources, and accessibility to other necessary resources. Contracts must not be made with parties who are suspended or debarred.

    (2) Design/build method. The Design/Build Method, where the same person or entity provides design and engineering work, as well as construction or installation, may be used with Agency written approval.

    (i) Concurrence information. The Applicant will request Agency concurrence by providing the Agency at least the information specified in paragraphs (e)(2)(i)(A) through (H) of this section.

    (A) The grantee's written request to use the Design/Build Method with a description of the proposed method.

    (B) A proposed scope of work describing in clear, concise terms the technical requirements for the contract. It shall include a nontechnical statement summarizing the work to be performed by the contractor, the results expected, and a proposed construction schedule showing the sequence in which the work is to be performed.

    (C) A proposed firm-fixed-price contract for the entire project which provides that the contractor will be responsible for any extra cost which result from errors or omissions in the services provided under the contract, as well as compliance with all Federal, State, local, and Tribal requirements effective on the contract execution date.

    (D) Where noncompetitive negotiation is proposed and found, by the Agency, to be an acceptable procurement method, then the Agency will evaluate documents indicating the contractor's performance on previous similar projects in which the contractor acted in a similar capacity.

    (E) A detailed listing and cost estimate of equipment and supplies not included in the construction contract but which are necessary to properly operate the project.

    (F) Evidence that a qualified construction Inspector who is independent of the contractor has or will be hired.

    (G) Preliminary plans and outline specifications. However, final plans and specifications must be completed and reviewed by the Agency prior to the start of construction.

    (H) The grantee's attorney's opinion and comments regarding the legal adequacy of the proposed contract documents and evidence that the grantee has the legal authority to enter into and fulfill the contract.

    (ii) Agency concurrence of design/build method. The Agency will review the material submitted by the Applicant. When all items are acceptable, the Agency approval official will concur in the use of the Design/Build Method for the proposal.

    (iii) Forms used. Agency approved contract documents must be used provided they are customarily used in the area and protect the interest of the Applicant and the Agency with respect to compliance with items such as the drawings, specifications, payments for work, inspections, completion, nondiscrimination in construction work, and acceptance of the work. The Agency will not become a party to a construction contract or incur any liability under it. No contract shall become effective until concurred, in writing, by the Agency. Such concurrence statement must be attached to and made a part of the contract.

    (iv) Contract provisions. Contracts will have a listing of attachments and must contain the following:

    (A) The contract sum;

    (B) The dates for starting and completing the work;

    (C) The amount of liquidated damages, if any, to be charged;

    (D) The amount, method, and frequency of payment;

    (E) Surety provisions that meet the requirements of paragraph (a)(3) of this section;

    (F) The requirement that changes or additions must have prior written approval of the Agency as identified in the letter of conditions;

    (G) Contract review and concurrence. The grantee's attorney will review the executed contract documents, including performance and payment bonds, and will certify that they are in compliance with Federal, State, or Tribal law, and that the persons executing these documents have been properly authorized to do so. The contract documents, engineer's recommendation for award, and bid tabulation sheets will be forwarded to the Agency for concurrence prior to awarding the contract. All contracts will contain a provision that they are not effective until they have been concurred, in writing, by the Agency;

    (H) This part does not relieve the grantee of any responsibilities under its contract. The grantee is responsible for the settlement of all contractual and administrative issues arising out of procurement entered into in support of Agency funding. These include, but are not limited to, source evaluation, protests, disputes, and claims. Matters concerning violation of laws are to be referred to the applicable local, State, Tribal, or Federal authority; and

    (3) Construction management. Construction managers as a constructor (CMc) acts in the capacity of a general contractor and is financially and professionally responsible for the construction. This type of construction management is also referred to as construction manager “At Risk.” The construction contract is between the grantee and the CMc. The CMc in turn subcontracts for some or all of the work. The CMc will need to carry the Agency required 100 percent surety and insurance, as required under paragraph (a)(3) of this section. Projects using construction management must follow the requirements of (e)(2)(i) through (iv) of this section.

    (f) Procurement methods. Procurement must be made by one of the following methods: competitive sealed bids (formal advertising); competitive negotiation; or noncompetitive negotiation. Competitive sealed bids (formal advertising) are the preferred procurement method for construction contracts.

    (1) Competitive sealed bids. In competitive sealed bids (formal advertising), sealed bids are publicly solicited and a firm-fixed-price contract (lump sum or unit price) is awarded to the responsible bidder whose bid, conforming with all the material terms and conditions of the invitation for bids, is lowest, price and other factors considered. When using this method, the following will apply:

    (i) At a sufficient time prior to the date set for opening of bids, bids must be solicited from an adequate number of qualified sources. In addition, the invitation must be publicly advertised.

    (ii) The invitation for bids, including specifications and pertinent attachments, must clearly define the items or services needed in order for the bidders to properly respond to the invitation under paragraph (f)(1) of this section.

    (iii) All bids must be opened publicly at the time and place stated in the invitation for bids.

    (iv) A firm-fixed-price contract award must be made by written notice to that responsible bidder whose bid, conforming to the invitation for bids, is lowest. When specified in the bidding documents, factors such as discounts and transportation costs will be considered in determining which bid is lowest.

    (v) The Applicant, with the concurrence of the Agency, will consider the amount of the bids or proposals, and all conditions listed in the invitation. On the basis of these considerations, the Applicant will select and notify the lowest responsible bidder. The contract will be awarded using an Agency-approved form.

    (vi) Any or all bids may be rejected by the grantee when it is in their best interest.

    (2) Competitive negotiation. In competitive negotiations, proposals are requested from a number of sources. Negotiations are normally conducted with more than one of the sources submitting offers (offerors). Competitive negotiation may be used if conditions are not appropriate for the use of formal advertising and where discussions and bargaining with a view to reaching agreement on the technical quality, price, other terms of the proposed contract and specifications are necessary. If competitive negotiation is used for procurement, the following requirements will apply:

    (i) Proposals must be solicited from two qualified sources, unless otherwise approved by the Agency, to permit reasonable competition consistent with the nature and requirements of the procurement.

    (ii) The Request for Proposal must identify all significant evaluation factors, including price or cost where required, and their relative importance.

    (iii) The grantee must provide mechanisms for technical evaluation of the proposals received, determination of responsible offerors for the purpose of written or oral discussions, and selection for contract award.

    (iv) Award may be made to the responsible offeror whose proposal will be most advantageous to the grantee, price and other factors considered. Unsuccessful offerors must be promptly notified.

    (v) Owners may utilize competitive negotiation procedures for procurement of architectural/engineering and other professional services, whereby the offerors' qualifications are evaluated and the most qualified offeror is selected, subject to negotiations of fair and reasonable compensation.

    (3) Noncompetitive negotiation. Noncompetitive negotiation is procurement through solicitation of a proposal from only one source. Noncompetitive negotiation may be used when the award of a contract is not feasible under small acquisition and construction procedures, competitive sealed bids (formal advertising) or competitive negotiation procedures. Circumstances under which a contract may be awarded by noncompetitive negotiations are limited to the following:

    (i) After solicitation of a number of sources, competition is determined inadequate; or

    (ii) No acceptable bids have been received after formal advertising.

    (4) Additional procurement methods. The grantee may use additional innovative procurement methods provided the grantee receives prior written approval from the Agency. Contracts will have a listing of attachments and the minimum provisions of the contract will include:

    (i) The contract sum;

    (ii) The dates for starting and completing the work;

    (iii) The amount of liquidated damages to be charged;

    (iv) The amount, method, and frequency of payment;

    (v) Whether or not surety bonds will be provided; and

    (vi) The requirement that changes or additions must have prior written approval of the Agency.

    (g) Contracts awarded prior to applications. Owners awarding construction or other procurement contracts prior to filing an application, must provide evidence that is satisfactory to the Agency that the contract was entered into without intent to circumvent the requirements of Agency regulations.

    (1) Modifications. The contract shall be modified to conform to the provisions of this subpart. Where this is not possible, modifications will be made to the extent practicable and, as a minimum, the contract must comply with all State and local laws and regulations as well as statutory requirements and executive orders related to the Agency financing.

    (2) Consultant's certification. Provide a certification by an engineer, licensed in the State where the facility is constructed, that any construction performed complies fully with the plans and specifications.

    (3) Owner's certification. Provide a certification by the owner that the contractor has complied with applicable statutory and executive requirements related to Agency financing.

    (h) Contract administration. Contract administration must comply with 7 CFR 1780.76. If another authority, such as a Federal, State, or Tribal agency, is providing funding and requires oversight of inspections, change orders, and pay requests, the Agency will accept copies of their reports or forms as meeting oversight requirements of the Agency.

    [79 FR 78255, Dec. 29, 2014, as amended at 81 FR 11052, Mar. 2, 2016]

    a) Inspections. Grantees must permit periodic inspection of the project records and operations by a representative of the Agency.

    (b) Programmatic changes. Grantees may make changes to an approved project's costs, scope, contractor, or vendor subject to the provisions specified in paragraphs (b)(1) through (3) of this section. If the changes result in lowering the project's score to below what would have qualified the application for award, the Agency will not approve the changes.

    (1) Prior approval. The grantee must obtain prior Agency approval for any change to the scope, contractor, or vendor of the approved project. Changes in project cost will require Agency approval as outlined in paragraph (b)(1)(iii) of this section.

    (i) Grantees must submit requests for programmatic changes in writing to the Agency for Agency approval.

    (ii) Failure to obtain prior Agency approval of any such change could result in such remedies as suspension, termination, and recovery of grant funds.

    (iii) Prior Agency approval is required for all increases in project costs. Prior Agency approval is required for a decrease in project cost only if the decrease would have a negative effect on the long-term viability of the project. A decrease in project cost that does not have a negative impact on long-term viability requires Agency review and approval prior to disbursement of funds.

    (2) Changes in project cost or scope. If there is a significant change in project cost or any change in project scope, then the grantee's funding needs, eligibility, and scoring, as applicable, will be reassessed. Decreases in Agency funds will be based on revised project costs and other factors, including Agency regulations used at the time of grant approval.

    (3) Change of contractor or vendor. When seeking a change, the grantee must submit to the Agency a written request for approval. The proposed contractor or vendor must have qualifications and experience acceptable to the Agency. The written request must contain sufficient information, which may include a revised technical report as required under § 4280.118(e), 4280.119(b)(4), 4280.120(b)(3), or 4280.120(b)(4), as applicable, to demonstrate to the Agency's satisfaction that such change maintains project integrity. If the Agency determines that project integrity continues to be demonstrated, the grantee may make the change. If the Agency determines that project integrity is no longer demonstrated, the change will not be approved and the grantee has the following options: Continue with the original contractor or vendor; find another contractor or vendor that has qualifications and experience acceptable to the Agency to complete the project; or terminate the grant by providing a written request to the Agency. No additional funding will be available from the Agency if costs for the project have increased. The Agency decision will be provided in writing.

    (c) Transfer of ownership. After the Financial Assistance Agreement for the project has been executed, the grantee may request, in writing, a transfer of the Financial Assistance Agreement to another entity. Subject to Agency approval provided in writing, the Financial Assistance Agreement may be transferred to another entity provided:

    (1) The entity is determined by the Agency to be an eligible entity under this subpart; and

    (2) The type of RES or EEI technology and the scope of the project for which the Agency funds will be used remain unchanged.

    (d) Disposition of acquired property. Grantees must abide by the disposition requirements outlined in Departmental Regulations.

    (e) Financial management system and records. The grantee must provide for financial management systems and maintain records as specified in paragraphs (f)(1) and (2) of this section.

    (1) Financial management system. The grantee will provide for a financial system that will include:

    (i) Accurate, current, and complete disclosure of the financial results of each grant;

    (ii) Records that identify adequately the source and application of funds for grant-supporting activities, together with documentation to support the records. Those records must contain information pertaining to grant awards and authorizations, obligations, unobligated balances, assets, liabilities, outlays, and income; and

    (iii) Effective control over and accountability for all funds. The grantee must adequately safeguard all such assets and must ensure that funds are used solely for authorized purposes.

    (2) Records. The grantee will retain financial records, supporting documents, statistical records, and all other records pertinent to the grant for a period of at least 3 years after completion of grant activities except that the records must be retained beyond the 3-year period if audit findings have not been resolved or if directed by the United States. The Agency and the Comptroller General of the United States, or any of their duly authorized representatives, must have access to any books, documents, papers, and records of the grantee that are pertinent to the specific grant for the purpose of making audit, examination, excerpts, and transcripts.

    (f) Audit requirements. If applicable, grantees must provide an annual audit in accordance with 7 CFR part 3052. The Agency may exercise its right to do a program audit after the end of the project to ensure that all funding supported eligible project costs.

    (g) Grant disbursement. As applicable, grantees must disburse grant funds as scheduled in accordance with the appropriate construction and inspection requirements in §§ 4280.119, 4280.120 or 4280.125 as applicable. Unless required by third parties providing cost sharing payments to be provided on a pro-rata basis with other funds, grant funds will be disbursed after all other funds have been expended.

    (1) Unless authorized by the Agency to do so, grantees may submit requests for reimbursement no more frequently than monthly. Ordinarily, payment will be made within 30 days after receipt of a proper request for reimbursement.

    (2) Grantees must not request reimbursement for the Federal share of amounts withheld from contractors to ensure satisfactory completion of work until after it makes those payments.

    (3) Payments will be made by electronic funds transfer.

    (4) Grantees must use SF-271, “Outlay Report and Request for Reimbursement for Construction Programs,” or other format prescribed by the Agency to request grant reimbursements. Fund requests must at a minimum include documentation of costs and evidence of payment(s), including payment date(s). Failure to provide sufficient documentation of costs and evidence of payment, including payment date, may result in denied reimbursement.

    (5) For a grant awarded to a project with total project costs of $200,000 and greater, grant funds will be disbursed in full after the project is completed, is operational, and has met or exceeded the steady state operating level as set out in the grant award requirements. Grant funds may also be disbursed through 90 percent of grant disbursement. The final 10 percent of grant funds will be held by the Agency until construction of the project is completed, the project is operational, and the project has met or exceeded the steady state operating level as set out in the grant award requirements. In addition, the Agency reserves the right to request additional information or testing if upon a final site visit or review of documentation, the 30-day steady state operating level is not found acceptable to the Agency.

    (h) Monitoring of project. Grantees are responsible for ensuring that all activities are performed within the approved scope of work and that funds are only used for approved purposes.

    (1) Grantees shall constantly monitor performance to ensure that:

    (i) Time schedules are being met;

    (ii) Projected work is being accomplished by projected time periods;

    (iii) Financial resources are being appropriately expended by contractors (if applicable); and

    (iv) Any other performance objectives identified in the scope of work are being achieved.

    (2) To the extent that resources are available, the Agency will monitor grantees to ensure that activities are performed in accordance with the Agency-approved scope of work and to ensure that funds are expended for approved purposes. The Agency's monitoring of grantees neither:

    (i) Relieves the grantee of its responsibilities to ensure that activities are performed within the scope of work approved by the Agency and that funds are expended for approved purposes only; nor

    (ii) Provides recourse or a defense to the grantee should the grantee conduct unapproved activities, engage in unethical conduct, engage in activities that are or that give the appearance of a conflict of interest, or expend funds for unapproved purposes.

    (i) Reporting requirements. Financial and project performance reports must be provided by grantees and contain the information specified in paragraphs (i)(1) through (3) of this section.

    (1) Federal financial reports. Between grant approval and completion of project (i.e., construction), SF-425, “Federal Financial Report” will be required of all grantees as applicable on a semiannual basis. The grantee will complete the project within the total sums available to it, including the grant, in accordance with the scope of work and any necessary modifications thereof prepared by grantee and approved by the Agency.

    (2) Project performance reports. Between grant approval and completion of project (i.e., construction), grantees must provide semiannual project performance reports and a final project development report containing the information specified in paragraphs (i)(2)(i) and (ii) of this section. These reports are due 30 working days after June 30 and December 31 of each year.

    (i) Semiannual project performance reports. Each semiannual project performance report must include the following:

    (A) A comparison of actual accomplishments to the objectives for that period;

    (B) Reasons why established objectives were not met, if applicable;

    (C) Reasons for any problems, delays, or adverse conditions which will affect attainment of overall program objectives, prevent meeting time schedules or objectives, or preclude the attainment of particular objectives during established time periods. This disclosure must be accompanied by a statement of the action taken or planned to resolve the situation; and

    (D) Objectives and timetables established for the next reporting period.

    (ii) Final project development report. The final project development report must be submitted 90 days after project completion and include:

    (A) A detailed project funding and expense summary; and

    (B) A summary of the project's installation/construction process, including recommendations for development of similar projects by future Applicants to the program.

    (3) Project completion requirements. Once the project has been constructed, the grantee must provide the Agency as applicable via form RD 4280-3D “Annual Outcome Project Performance Certification”, a certification that their system has for the past year performed at the steady operating level as described in the technical report of their application, and whether projected jobs created or saved have occurred, or certify that it has not performed as described. If it has not performed, a description of the circumstances which have occurred and affected system performance must be reported, along with the actual performance of the subject REAP project, and the actual number of jobs created or saved as a direct result of the REAP project.

    (i) RES. Three total annual outcome project performance certifications or reports are required for RES projects. The first is due at the completion of the first full calendar year following the year in which the project was completed. The remaining are required for subsequent calendar years.

    (ii) EEI. Two total annual outcome performance certifications or reports are required for EEI projects. The first is due at completion of the first full calendar year following the year in which the project was completed. The second is required for the subsequent calendar year.

    (j) Grant close-out. Grant close-out must be performed in accordance with the requirements specified in 2 CFR part 200.