§ 773.7 - Review of permit applications.
-
§ 773.7 How and when will the regulatory authority review and make a decision on an application for a permit, permit revision, or permit renewal?Review of permit applications.
(a) General. The regulatory authority will review an application for a permit, permit revision, or permit renewal; and issue a written decision granting, requiring modification of, or denying the application. Before making this decision, the regulatory authority must consider any written comments and objections submitted, as well as the ; and records of any informal conference or hearing held on the application .
(b) When will the regulatory authority make a decision on a permit application ?
(1)regulatory authority will issue a decision on the applicationand issue a written decision, within a reasonable time set by the regulatory authority, either granting, requiring modification of, or denying the application. If an informal conference is held under § 773.6(c) of this part, the
decision will be made within 60 days of the close of the conference.
(c) Who has the burden of proof ? You, the(
2) If no informal conference is held under § 773.6(c) of this part, the regulatory authority must issue a decision on the application within a reasonable time established in the regulatory program. In determining what constitutes a reasonable time, the regulatory authority must consider the following five factors:(i) The time needed for proper site investigations.
(ii) The complexity of the permit application.
(iii) Whether there are any written objections on file.
(iv) Whether the application previously has been approved or disapproved, in whole or in part.
(v) The time required for coordination of permitting activities with other agencies under § 773.5 of this part.
,b) The applicant for a permit
, or the transfer, assignment, or sale of permit rights,or revision of a permit
yourshall have the burden of establishing that
his application is in compliance with all the requirements of the regulatory program.
[48 FR 44391, Sept. 28, 1983, as amended at 65 FR 79663, Dec. 19, 2000; 72 FR 68029, Dec. 3, 2007; 81 FR 93323, Dec. 20, 2016; 82 FR 54937, Nov. 17, 2017]