§ 285.614 When may I begin conducting activities under my approved SAP?
(a) You may begin conducting the activities approved in your SAP following BOEM approval of your SAP.
(b) If you are installing a facility or a combination of facilities deemed by BOEM to be complex or significant, as provided in 30 CFR 585.613(a)(1), you must comply with the requirements of subpart G of this part and submit your safety management system required by § 285.810 before construction may begin.