Appendix A to Part 602 - Schedule of Renewal Applications and Reports


Latest version.
  • Appendix A to Part 602 - Schedule of Renewal Applications and Reports

    Type When due Number of copies for awarding office
    1. Summary: 200 words on scope and purpose (Notice of Energy R&D Project) Immediately after a grant is awarded and with each application for renewal 3
    2. Renewal period ends 6 months before the budget 8
    3. Progress Report period (or as part of a renewal application) 90 days prior to the next budget period 3
    4. Other progress reports, brief topical reports, etc. (Designated when significant results develop or when work has direct programmatic impact) As deemed appropriate by DOE or the recipient 3
    5. Reprints, Conference Same as 4. above 3
    6. Final report of the project Within 90 days after completion 3
    7. Financial Status Report (FSR) Within 90 days after completion of the project period; for budget periods exceeding 12 months an FSR is also required within 90 days after the first 12-month period 3