Code of Federal Regulations (Last Updated: July 5, 2024) |
![]() |
Title 10 - Energy |
![]() |
Chapter I - Nuclear Regulatory Commission |
![]() |
Part 52 - Licenses, Certifications, and Approvals for Nuclear Power Plants |
![]() |
Subpart F - Manufacturing Licenses |
§ 52.173 - Duration of manufacturing license.
Latest version.
-
§ 52.173 Duration of manufacturing license.
A manufacturing license issued under this subpart may be valid for not less than 5, nor more than 15 years from the date of issuance. A holder of a manufacturing license may not initiate the manufacture of a reactor less than 3 years before the expiration of the license even though a timely application for renewal has been docketed with the NRC. Upon expiration of the manufacturing license, the manufacture of any uncompleted reactors must cease unless a timely application for renewal has been docketed with the NRC.