§ 305.16 - Construction progress schedule.  


Latest version.
  • If requested by EDA, the recipient will secure from the contractor or A/E and furnish a copy to EDA of the estimated construction progress chart and a schedule of amounts for contract payments. The construction progress chart should be updated monthly by the recipient, the A/E or the contractor, and an up-to-date copy furnished to EDA quarterly throughout the construction of the project.