§ 305.18 - Occupancy prior to completion.  


Latest version.
  • If the project or any part of it is to be occupied or used prior to the project's acceptance from the contractor, the recipient must notify EDA of the intent to occupy or use the facility and the effective date of the occupancy or use, secure the written consent of the contractor; secure an endorsement from the insurance carrier and consent of the surety company permitting occupancy or use during the period of construction; secure permanent fire and extended coverage insurance and, when required, secure a permit to occupy the facility from the appropriate authority, e.g. the local building inspector.