§ 305.21 - Controlling budget.  


Latest version.
  • The tabulation of estimated project costs contained in the EDA grant award is the controlling budget for the project.

    (a) Budget line item revisions, including the addition of a new line item, which do not involve a change of scope may be approved by EDA if no new EDA funds are involved; another budget line item (preferably the contingency line item, although this is not mandatory) has funds which can be used without significantly adversely affecting the object of that line item; and unless the line item that is proposed to be supplemented is supplemented, the activity associated with that line item cannot be completed.

    (b) The recipient shall notify EDA of any proposed transfer of funds from one budget line item to another. The recipient's attention is called to the fact that the addition of a new line item to the approved budget may involve an impermissible change of scope and, therefore, may result in such costs being excluded from EDA's participation. Accordingly, the recipient is advised to discuss the need to add a new line item to the approved budget with EDA regional office staff before any costs are incurred under such new line item.