§ 316.19 - Project administration by District organization.


Latest version.
  • When an Economic Development District is not a recipient or co-recipient of an award for a project involving construction, the District organization may administer the project for such recipient if the following conditions are met, as determined by EDA:

    (a) The recipient has requested (either in the application or by separate written request) that the district organization for the area in which the project is located perform the project administration;

    (b) The recipient certifies and EDA finds that:

    (1) Administration of the project is beyond the capacity of the recipient's current staff to perform and would require hiring additional staff or contracting for such services,

    (2) No local organization/business exists that would be able to administer the project in a more efficient or cost-effective manner than the staff of the district, and

    (3) The staff of the district would administer the project themselves, without subcontracting the work out;

    (c) EDA approves the request either by approving the application in which the request is made, or by separate specific written approval; and

    (d) The allowable costs for the administration of the project by the district organization staff will not exceed the customary and reasonable amount that would be allowable if the district were the recipient.