§ 1216.313 - Implementing and monitoring the decision.  


Latest version.
  • (a) Section 1505.3 of the CEQ Regulations provides for agency monitoring to assure that mitigation measures and other commitments associated with the decision and its implementation and described in the EIS are carried out and have the intended effects.

    (b) The responsible Headquarters official shall, as necessary, conduct the required monitoring and shall provide periodic reports as required by the Associate Administrator for Management.

    (c) If the monitoring activity indicates that resulting environmental effects differ from those described in the current documents, the Headquarters official shall reassess the environmental impact and consult with the Associate Administrator for Management to determine the need for additional mitigation measures and whether to prepare a supplement to the EIS (see 40 CFR 1502.9 of the CEQ Regulations).