    (a) NASA permits acquisition of special purpose and general purpose equipment specifically required for use exclusively for research activities.

    (1) Acquisition of special purpose or general purpose equipment costing in excess of $5,000 (unless a lower threshold has been established by the Recipient) and not included in the approved proposal budget, requires the prior approval of the NASA Grant Officer. Grant awards under the Federal Demonstration Partnership are exempt from this requirement. Requests to the NASA Grant Officer for the acquisition of equipment shall be supported by written documentation setting forth the description, purpose, and acquisition value of the equipment, and including a written certification that the equipment will be used exclusively for research, activities. (A change in the model number of a prior approved piece of equipment does not require resubmission for that item.)

    (2) Special purpose and general purpose equipment costing in excess of $5,000 (unless a lower threshold has been established by the Recipient) acquired by the recipient under a grant or cooperative agreement for the purpose of research shall be titled to the Recipient as “exempt” without further obligation to NASA, including reporting of the equipment, in accordance with §1260.133(b). Special purpose or general purpose equipment costing in excess of $5,000 (unless a lower threshold has been established by the Recipient) acquired by the Recipient under a grant or cooperative agreement for non-research work shall be titled to the Recipient in accordance with §1260.134.

    (3) Special purpose or general purpose equipment acquired by the Recipient with grant funds, valued under $5,000 (unless a lower threshold is established by the Recipient) are classified as “supplies,” do not require the prior approval of the NASA Grant Officer, shall vest in the Recipient and will be titled to the Recipient in accordance with §1260.135.

    (4) Grant funds may be expended for the acquisition of land or interests therein or for the acquisition and construction of facilities only under a facilities grant, as defined in §1260.12(c)(4).

    (b) The Recipient shall submit an annual Inventory Report, to be received no later than October 15 of each year, which lists all reportable (non-exempt equipment and/or Federally owned property) in its custody as of September 30. Negative responses for annual Inventory Reports (when there is no reportable equipment) are not required. A Final Inventory Report of Federally Owned Property, including equipment where title was taken by the Government, will be submitted by the Recipient no later than 60 days after the expiration date of the grant. Negative responses for Final Inventory Reports are required.

    (1) All reports will include the information listed in paragraph (f)(1) of §1260.134, Equipment. No specific report form or format is required, provided that all necessary information set forth at §1260.134(f)(1) is provided.

    (2) The original of each report shall be submitted to the Deputy Chief Financial Officer (Finance). Copies shall be furnished to the Center Industrial Property Officer and to ONR.

    [End of provision]

    [65 FR 62900, Oct. 19, 2000, as amended at 69 FR 5016, Feb. 3, 2004]