§ 12.37 - Comprehensive assessment.  


Latest version.
  • § 12.37 Report of the independent consultant.Comprehensive assessment.

    A comprehensive assessment must include:

    (a) General requirement. Following inspection of a project development as required under this subpart, the independent consultant must prepare a report and the licensee must file three copies of that report with the Regional Engineer. The report must conform to the provisions of this section and be satisfactory to the authorized Commission representative.

    (b) General information in the initial report.

    (1) The initial report filed under this subpart for any project development must contain:

    (i) A description of the project development;

    (ii) A map of the region indicating the location of the project development;

    (iii) Plans, elevations, and sections of the principal project works;

    (iv) A summary of the design assumptions, design analyses, spillway design flood, and the factors of safety used to evaluate the structural adequacy and stability of the project works; and

    (v) A summary of the geological conditions that may affect the safety of the project works.

    (2) To the extent that the information and analyses required in paragraph (b)(1) of this section, are contained in a report of an independent consultant prepared and filed in compliance with Commission regulations in effect before March 1, 1981 the information and analyses may be incorporated by specific reference into the first report prepared and filed under this subpart.

    (c) Information required for all reports. Any report of an independent consultant filed under this subpart must contain the information specified in this paragraph.

    (1) Monitoring information. The report must contain monitoring information that includes time-versus-reading graphs depicting data compiled from any existing critical or representative monitoring instruments that measure the behavior, movement, deflection, or loading of project works or from which the stability, performance, or functioning of the structures may be determined.

    (i) Any monitoring data plotted on graphs must be presented in a manner that will facilitate identification and analysis of trends. The data may be summarized to facilitate graphical representation.

    (ii) Plan and sectional drawings of project structures sufficient to show the location of all critical or representative existing monitoring instruments must be included. If these drawings have been included in a previous report prepared and filed by an independent consultant, they may be incorporated by specific reference to that earlier report.

    (2) Analyses. The report must:

    (i) Analyze the safety of the project works and the maintenance and methods of operation of the development fully in light of the independent consultant's reviews, field inspections, assessments, and evaluations described in § 12.35;

    (ii) Identify any changes in the information and analyses required by paragraph (b) of this section that have occurred since the last report by an independent consultant under this subpart and analyze the implications of those changes; and

    (iii) Analyze the adequacy of existing monitoring instruments, periodic observation programs, and other methods of monitoring project works and conditions effecting the safety of the project or project works with respect to the development.

    (3) Incorporation by reference. To the extent that conditions, assumptions, and available information have not changed since the last previous report by an independent consultant under this subpart, the analyses required under paragraphs (c)(2)(i) and (ii) of this section may be incorporated by specific reference to the last previous report.

    (4) Recommendations. Based on the independent consultant's field observations and evaluations of the project works and the maintenance, surveillance, and methods of operation of the development, the report must contain the independent consultant's recommendations on:

    (i) Any corrective measures necessary for the structures or for the maintenance or surveillance procedures or methods of operation of the project works;

    (ii) A reasonable time to carry out each corrective measure; and

    (iii) Any new or additional monitoring instruments, periodic observations, or other methods of monitoring project works or conditions that may be required.

    (5) Dissenting views. If the inspection and report were conducted and prepared by more than one independent consultant, the report must clearly indicate any dissenting views concerning the analyses or recommendations of the report that might be held by any individual consultant.

    (6) List of participants. The report must identify all professional personnel who have participated in the inspection of the project or in preparation of the report and the independent consultant who directed those activities.

    (7) Statement of independence. The independent consultant must declare that all conclusions and recommendations in the report are made independently of the licensee, its employees, and its representatives.

    (8) Signature. The report must be signed by each independent consultant responsible for the report.

    Review of prior reports and analyses of record. The independent consultant team must review and consider all relevant reports on the safety of the development made by or written under the direction of Federal or state agencies, submitted under Commission regulations, or made by other consultants. The licensee must provide to the independent consultant team all information, reports, and analyses of record necessary to fulfill the requirements of this section.

    (1) In addition to the requirements of § 12.35(a), the independent consultant team must have a full understanding of the risk associated with the project works.

    (2) The independent consultant team shall perform a detailed review of the as-built drawings; monitoring data; and the methods, assumptions, calculations, results, and conclusions of the analyses of record pertaining to:

    (i) Geology and seismicity;

    (ii) Hydrology and hydraulics;

    (iii) Stability and structural integrity of project works; and

    (iv) Any other analyses relevant to the safety, stability, and operation of project works.

    (b) Physical field inspection. The independent consultant team must perform a physical field inspection that complies with § 12.35(b).

    (c) Review of surveillance and monitoring plan and data. The independent consultant team must perform a review of surveillance and monitoring plan and data that complies with § 12.35(c).

    (d) Review of dam and public safety programs. The independent consultant team must perform a review of dam and public safety programs that complies with § 12.35(d).

    (e) Supporting Technical Information Document. The comprehensive assessment shall include a review of the Supporting Technical Information Document.

    (f) Potential failure mode analysis. The comprehensive assessment shall include a potential failure mode analysis.

    (g) Risk analysis. The comprehensive assessment shall include a risk analysis. The Regional Engineer may, for good cause shown, grant a waiver of the requirement to complete a risk analysis. Any petition for waiver under this paragraph must be filed in accordance with § 385.207 of this chapter.