Code of Federal Regulations (Last Updated: November 8, 2024) |
Title 18 - Conservation of Power and Water Resources |
Chapter XIII - Tennessee Valley Authority |
Part 1308 - Contract Disputes |
Subpart C - Board of Contract Appeals |
§ 1308.24 - Undue delay in Contracting Officer's decision.
-
§ 1308.24 Undue delay in Contracting Officer's decision.
(a) If there is an undue delay by a Contracting Officer in issuing a decision on a claim, the Contractor may request the Chairman to direct the Contracting Officer to issue a decision within a specified period of time.
(b) A request under this section shall:
(1) Be in writing;
(2) State the date on which the claim was submitted to the Contracting Officer.
(3) State the date suggested for issuance of a decision by the Contracting Officer.
(c) TVA may reply to a motion under this section within 5 days after its receipt.
(d) The Chairman shall issue a written decision on the request. If granted, the decision shall specify the date by which the Contracting Officer's decision is to be rendered, and a copy shall be served on the Contracting Officer.