§ 157.103 - Terms and conditions; other requirements.
-
(a)
Non-exclusivity of certificates issued under this subpart. A certificate issued pursuant to this subpart must be non-exclusive and must provide that it in no way prejudices any application for any other certificate under the Natural Gas Act or for authorization under the Natural Gas Policy Act.(b)
Certificate limited to qualifying facilities and new service. A certificate issued under this subpart provides only for authorization to construct or acquire and operate qualifying facilities and to provide new service.(c)
Allocation of joint costs. To the extent the service proposed will utilize existing facilities, the cost of those facilities will be allocated among theservices provided under this subpart and other services provided. (d)
Rates— (1)General. Any rate filed for new service under this subpart must comply with the conditions of this paragraph.(2)
Rate objectives. Maximum rates for both peak and off-peak periods must be designed, to the maximum extent possible, to achieve the following three objectives:(i) Rates for service during peak periods should ration capacity;
(ii) Rates for firm service during off-peak periods and for interruptible service during all periods should maximize through-put; and
(iii) The certificate holder's revenue requirement allocated to firm and interruptible services should be attained by providing the projected units of service in peak and off-peak periods at the maximum rate for each service.
(3)
Volumetric rates. Except for a reservation charge for firm transportation service consistent with the conditions in § 284.8(d), any rate filed for new service must be a one-part rate that recovers the costs allocated to the new service to the extent that the projected units of that service are actually purchased and may not include a demand charge, a minimum bill or minimum take provision or any other provision that has the effect of guaranteeing revenue.(4)
Based on projected units of service. Any rate filed for new service must be designed to recover costs on the basis of projected units of service. The units projected for the new service in the initial rates filed under this subpart may be increased in a subsequent rate filing but may not be decreased.(5)
Differentiation due to time and distance. Any rate filed for new service must reasonably reflect any material variation in the cost of providing the service due to:(i) Whether the new service is provided during a peak or an off-peak period; and
(ii) The distance over which the new service is provided.
(6)
Cost basis for rates. (i) Any maximum rate filed for new service must be designed to recover, on a unit basis, solely those costs which are properly allocated to that service.(ii) Any minimum rate for new service must be based on the average variable costs which are properly allocated to that service.
(7)
Rate flexibility. (i) Any rate schedule filed for new service must state a maximum rate and a minimum rate.(ii) The certificate holder may charge an individual customer for new service any rate that is neither greater than the maximum rate nor less than the minimum rate on file for that service.
(iii) The certificate holder may not file a revised or new rate designed to recover costs not recovered under rates previously in effect.
(iv) If, during any billing period, a certificate holder charges a rate or collects a reservation fee that is less than the maximum rate or fee that could be charged, the certificate holder must, within 45 days of the close of the billing period, file a report with the Commission identifying:
(A) The maximum rate or fee and the rate or fee actually charged during the billing period;
(B) The customer; and
(C) Any corporate affiliation between the customer and the certificate holder.
(8) Prohibitions against cost shifting. No costs originally allocated to a new service may subsequently be allocated to any other services without a filing under Subpart D of Part 154 and a determination by the Commission that the costs sought to be reallocated are in fact being incurred for the benefit of the other services.
(e)
No revenue guarantees for new sales service. No demand charge, reservation fee, minimum bill provision, minimum take provision, or any other provision that has effect of guaranteeing revenue may be imposed for firm or interruptible sales service provided under this subpart.(f)
Conditional pre-granted abandonment authority . (1) Subject to paragraph (f)(2) and (f)(3) of this section, if requested by the applicant in its application, any order issuing a certificate under this subpart must provide conditional pre-granted authority to abandon the proposed new service and qualifying facilities at the expiration of the contracts under-lying the new service.(2) At least forty-five days prior to the expiration of any contractual agreement with a customer to provide new service, a certificate holder that intends to abandon any part of the new service upon expiration of the contractual agreement for that service must provide the customer and the Commission with written notice of the proposed abandonment.
(3) A customer receiving notice of a proposed abandonment of new service to it may file a protest under § 157.106 of this subpart.
(g)
Flexible receipt point authority. (1) A certificate holder authorized to transport gas under a certificate issued pursuant to this subpart may at the request of the shipper and without prior notice:(i) Reduce or discontinue receipts of natural gas at a particular point from a supplier, and
(ii) Commence or increase receipts at a particular point from that supplier or any other supplier. The total natural gas volumes received by the interstate pipeline following any such reassignment must not exceed the total volume of natural gas that the certificate holder is authorized under the certificate issued pursuant to this subpart to transport on behalf of the shipper.
(2) The receipt points to which natural gas volumes may be reassigned under this paragraph include eligible facilities under § 157.208 of this part which are authorized to be constructed and operated pursuant to a certificate issued under subpart F of this part.
(h)
Flexible delivery point authority. (1) A certificate holder authorized to transport gas under a certificate issued pursuant to this subpart may at the request of the shipper and without prior notice:(i) Reduce or discontinue deliveries of natural gas to a particular delivery point; and
(ii) Commence or increase deliveries to a particular delivery point.
(2) The total natural gas volumes delivered by the certificate holder following any such reassignment must not exceed the total amount of natural gas that the certificate holder is authorized under the certificate issued pursuant to this section to transport on behalf of the shipper.
(3) The delivery points to which natural gas volumes may be reassigned under this paragraph include facilities authorized to be constructed and operated pursuant to a certificate issued under subpart F of this part.
(i)
Environmental compliance. Any certificate issued under this subpart is subject to the terms and conditions of § 157.206(d) of this chapter.(j)
Commencement of new service. Any authorized construction, extension, or acquisition of qualifying facilities must be completed and in actual operation by the applicant and any authorized operation, service, or sale must be actually undertaken and regularly performed by the applicant (within a period of time to be specified by the Commission in each order) from the issue date of the order issuing the certificate. The certificate holder may apply to the Director of the Office of Pipeline and Producer Regulation for an extension of this deadline.