§ 55.28 - Use of individual permits under section 404 of the Clean Water Act for HUD Executive Order 11990 processing where all wetlands are covered by the permit.


Latest version.
  • § 55.28 Use of individual permits under section 404 of the Clean Water Act for HUD Executive Order 11990 processing where all wetlands are covered by the permit.

    (a) Processing requirements. HUD (or the responsible entity subject to 24 CFR part 58) shall not be required to perform the steps at § 55.20(a) through (e) upon adoption by HUD (or the responsible entity) of the terms and conditions of a Section 404 permit so long as:

    (1) The project involves new construction on a property located outside of the 100-year floodplain (or the 500-year floodplain for critical actions);

    (2) The applicant has submitted, with its application to HUD (or to the recipient under programs subject to 24 CFR part 58), an individual Section 404 permit (including approval conditions) issued by the U.S. Army Corps of Engineers (USACE) (or by a State or Tribal government under Section 404(h) of the Clean Water Act) for the proposed project; and

    (3) All wetlands adversely affected by the action are covered by the permit.

    (b) Unless a project is excluded under § 55.12, processing under all of § 55.20 is required for new construction in wetlands that are not subject to section 404 of the Clean Water Act and for new construction for which the USACE (or a State or Tribal government under section 404(h) of the Clean Water Act) issues a general permit under Section 404.

    [78 FR 68734, Nov. 15, 2013]