§ 950.270 - Construction completion and settlement.  


Latest version.
  • (a) Final inspection. The IHA shall assure that all work is satisfactorily completed, in accordance with the terms of the construction contract, prior to scheduling a final inspection. The final inspection shall be made jointly by the IHA and the contractor. Where appropriate, the IHA shall notify tribal or local regulatory agencies, the BIA, the IHS, and HUD before this inspection to provide them with the opportunity to participate in the final inspection of all or part of the work. In a MH project, homebuyers shall also be invited to participate in the inspection of their homes, but acceptance shall be by the IHA. Maximum consideration shall be given to all homebuyer concerns.

    (b) Contract settlement. (1) If the final inspection discloses no deficiencies other than punch list items or seasonal completion items, the IHA shall, as soon as practical, develop an interim Certificate of Completion to enable partial settlement of the contract. The interim Certificate shall detail the items remaining and set forth a schedule for their completion, and shall allow the IHA to accept the units (or stage) for occupancy. Upon completion of the interim Certificate and receipt of the contractor's Certificate and Release, the IHA shall release the monies due the contractor/developer less withholdings in accordance with the construction contract.

    (2) The contractor/developer shall complete the punch list items in accordance with the time schedule contained in the interim Certificate. The IHA may pay the contractor/developer for items that are completed to the satisfaction of the IHA. If the IHA is satisfied that the applicable requirements of the construction contract and the interim Certificate have been met, the IHA shall prepare a final Certificate of Completion and release the amounts withheld to the contractor/developer.

    (c) Notification to HUD. (1) Upon acceptance of the project or any part thereof, the IHA shall notify HUD of such action. When all units within a project are accepted, the IHA shall provide a notification to HUD of the date the project was fully available for occupancy by residents.

    (2) The IHA shall notify HUD when all units in the project are occupied.