Code of Federal Regulations (Last Updated: May 6, 2024) |
Title 30 - Mineral Resources |
Chapter I - Mine Safety and Health Administration, Department of Labor |
SubChapter B - Testing, Evaluation, and Approval of Mining Products |
Part 18 - Electric Motor-Driven Mine Equipment and Accessories |
Subpart A - General Provisions |
§ 18.8 - Date for conducting investigation and tests.
Latest version.
-
§ 18.8 Date for conducting investigation and tests.
The date of receipt of an application will determine the order of precedence for investigation and testing. If an electrical machine component or accessory fails to meet any of the requirements, it shall lose its order of precedence. If an application is submitted to resume investigation and testing after correction of the cause of failure, it will be treated as a new application and the order of precedence for investigation and testing will be so determined.