§ 250.1743 - How do I certify that a site is clear of obstructions?


Latest version.
  • § 250.1743 How do I certify that a site is clear of obstructions?

    (a) For a well site, you must submit to the appropriate District Manager within 30 days after you complete the verification activities a form BSEE-0124, Application for Permit to Modify, to include the following information:

    (1) A signed certification that the well site area is cleared of all obstructions;

    (2) The date the verification work was performed and the vessel used;

    (3) The extent of the area surveyed;

    (4) The survey method used;

    (5) The results of the survey, including a list of any debris removed or a statement from the trawling contractor that no objects were recovered; and

    (6) A post-trawling job plot or map showing the trawled area.

    (b) For a platform or other facility site, you must submit the following information to the appropriate Regional Supervisor within 30 days after you complete the verification activities:

    (1) A letter signed by an authorized company official certifying that the platform or other facility site area is cleared of all obstructions and that a company representative witnessed the verification activities;

    (2) A letter signed by an authorized official of the company that performed the verification work for you certifying that it cleared the platform or other facility site area of all obstructions;

    (3) The date the verification work was performed and the vessel used;

    (4) The extent of the area surveyed;

    (5) The survey method used;

    (6) The results of the survey, including a list of any debris removed or a statement from the trawling contractor that no objects were recovered; and

    (7) A post-trawling job plot or map showing the trawled area.