§ 250.285 - How do I submit revised and supplemental EPs, DPPs, and DOCDs?


Latest version.
  • (a) Submittal. You must submit to the Regional Supervisor any revisions and supplements to approved EPs, DPPs, or DOCDs for approval, whether you initiate them or the Regional Supervisor orders them.

    (b) Information. Revised and supplemental EPs, DPPs, and DOCDs need include only information related to or affected by the proposed changes, including information on changes in expected environmental impacts.

    (c) Procedures. All supplemental EPs, DPPs, and DOCDs, and those revised EPs, DPPs, and DOCDs that the Regional Supervisor determines are likely to result in a significant change in the impacts previously identified and evaluated, are subject to all of the procedures under § 250.231 through § 250.235 for EPs and § 250.266 through § 250.273 for DPPs and DOCDs.