Code of Federal Regulations (Last Updated: July 5, 2024) |
Title 30 - Mineral Resources |
Chapter II - Bureau of Safety and Environmental Enforcement, Department of the Interior |
SubChapter B - Offshore |
Part 285 - [Reserved] |
Subpart F - Plans and Information Requirements |
Activities Under an Approved SAP |
§ 285.614 - When may I begin conducting activities under my approved SAP?
Latest version.
-
§ 285.614 When may I begin conducting activities under my approved SAP?
(a) You may begin conducting the activities approved in your SAP following BOEM approval of your SAP.
(b) If you are installing a facility or a combination of facilities deemed by BOEM to be complex or significant, as provided in 30 CFR 585.613(a)(1), you must comply with the requirements of subpart G of this part and submit your safety management system required by § 285.810 before construction may begin.