![]() |
Code of Federal Regulations (Last Updated: May 6, 2024) |
![]() |
Title 30 - Mineral Resources |
![]() |
Chapter II - Bureau of Safety and Environmental Enforcement, Department of the Interior |
![]() |
SubChapter B - Offshore |
![]() |
Part 285 - Renewable Energy and Alternate Uses of Existing Facilities on the Outer Continental Shelf |
![]() |
Subpart F - Information Requirements |
![]() |
Activities Under an Approved COP |
§ 285.636 - What notices must I provide BSEE following approval of my COP?
Latest version.
-
§ 285.636 What notices must I provide BSEE following approval of my COP?
You must notify BSEE in writing of the following events, within the time periods provided:
(a) No later than 30 days after commencing activities associated with the placement of facilities on the lease area under a Fabrication and Installation Report.
(b) No later than 30 days after completion of construction and installation activities under a Fabrication and Installation Report.
(c) At least 7 days before commencing commercial operations.