§ 285.910 - What must I do when I remove my facility?
Latest version.
-
§ 285.910 What must I do when I remove my facility?
(a) You must remove all facilities to a depth of 15 feet below the mudline, unless otherwise authorized by BSEE.
(b) Within 60 days after you remove a facility, you must verify to BSEE that you have cleared the site.