§ 585.223 What does BOEM do if there is a tie for the highest bid?
(a) Unless otherwise specified in the Final Sale Notice, except in the first stage of a two-stage bidding auction, if more than one bidder on a lease submits the same high bid amount, the winning bidder will be determined by a further round or stage of bidding as described in the Final Sale Notice.
(b) The winning bidder will be subject to final confirmation following determination of bid adequacy.