Activities Under an Approved GAP |
§ 585.652 - How long do I have to conduct activities under an approved GAP?
Latest version.
-
§ 585.652 How long do I have to conduct activities under an approved GAP?
After BOEM approves your GAP, you have:
(a) For a limited lease, the time period established under § 585.236(a)(2), unless we renew the operations period under §§ 585.425 through 585.429.
(b) For a ROW grant or RUE grant, the time provided in the terms of the grant.