§ 644.157 - Procedures.


Latest version.
  • § 644.157 Procedures.

    (a) ENG Form 1258, Right-of-Entry for Survey and Exploration, will be used to obtain authority from the owner of lands to be used for the purpose of making surveys, test borings, and other exploratory work as may be necessary to complete the particular investigation.

    (b) ENG Form 2803, Right-of-Entry for Construction, will be used to obtain authority from the owner of lands to be used for construction purposes when all of the following conditions apply:

    (1) A Real Estate Directive has been issued on an Army (military) or Air Force project, or the Chief of Engineers has approved acquisition in connection with a civil works project or for another Government agency.

    (2) The construction schedule does not allow sufficient time to secure the right of possession by normal acquisition procedures.

    (c) Upon execution of an ENG Form 2803, a copy thereof shall be forwarded to HQDA (DAEN-REA-L) WASH DC 20314 on Army Military and Air Force acquisitions, and in all other cases to HQDA (DAEN-REA-P) WASH DC 20314, together with a proposed schedule of final acquisition of the necessary interests in real estate. If final acquisition is not contemplated within six months from the date of the right-of-entry, an explanation should also be furnished as to the reason for the delay.

    (d) Division and District Engineers may modify ENG Forms 1258 and 2803, where necessary, to meet requirements of landowners, provided such modifications do not increase the scope of the liability or responsibility of the Government over that contained in the standard forms.

    (e) It is necessary to recognize not only the effects of entry upon a particular parcel of land, but also the effects of the passage of any vehicle (land, air, or water) on the area traversed. All possibilities of disturbing effects on the countryside shall be considered and routes selected to eliminate or minimize such disturbances.

    (f) Any cash settlements in lieu of restoration for damages, incurred under ENG Forms 1258 and 2803, will be consummated by supplemental agreement in accordance with subpart I.