§ 751.30 - Settlement procedures and third party responses.  


Latest version.
  • (a) Settlement procedures. In the interest of expeditious office administration, correspondence to carriers and contractors should be kept to a minimum. Normally, one rebuttal to a third party's denial of liability is sufficient, unless the carrier or contractor raises new arguments or provides new information.

    (1) Checks from third parties. Accept checks for the amount demanded from carriers and contractors. If a carrier or contractor forwards a check for less than the amount demanded, review the carrier's arguments for reducing liability to determine if they are acceptable. If the third party's basis for reducing liability is acceptable in the light of all evidence, deposit the check and dispatch the unearned freight letter, if applicable. Mark the front upper left-hand corner of the file as “CLOSED.”

    (2) Third party offers of settlement. If a carrier or contractor offers to settle the claim, review the carrier's arguments for reducing liability to determine if they are acceptable. If the third party's basis for reducing liability is acceptable in light of all evidence, inform the carrier that the offer is accepted, but that offset action will be initiated if a check for that amount is not received within 45 days. If a check in the amount acceptable to the Government is received, deposit it and dispatch the unearned freight letter, if applicable. Mark the front upper left-hand corner of the file as “CLOSED.” If a check in the proper amount is not received within 45 days, send the request to NAVMTO, Norfolk (or appropriate contract officer) for offset action (see § 751.32 of this part).

    (3) Unacceptable third party checks and offers of settlement. If a third party's basis for denying liability is not valid, respond to that carrier or contractor. Return unacceptable checks. Explain the reasons for not accepting the check or offer, and request the amount that is justified under the circumstances in the light of all the evidence. If a release was included, amend the release to the revised amount and sign, date, witness, and return it. Warn the carrier or contractor that the claim will be forwarded for offset action if a check for the amount justified under the circumstances is not received within 45 days. Suspend the file for 45 days and if a check in the proper amount is received, deposit it and dispatch the unearned freight letter, if applicable. If a check in the proper amount is not received within 45 days, request NAVMTO, Norfolk (or appropriate contract officer) to take offset action.

    (4) Third party denials of liability. Upon receipt, review the carrier or contractor's basis for denying liability in the light of all the evidence.

    (i) Acceptable third party reasons for denial. Mark the front upper left-hand corner of such files as “CLOSED.”

    (ii) Partially acceptable and unacceptable third party reasons for denial. If the carrier or contractor's basis for denying liability is acceptable only in part or is completely unacceptable, follow the procedures in subparagraph (3) above, requesting the amount that is justified under the circumstances in the light of all the evidence. If a response is not received within 45 days, or if the third party's reply is not responsive, request NAVMTO, Norfolk (or appropriate contract officer) take offset action as described above.

    (b) Depreciation. In determining payments to claimants, the depreciation rates from the Allowance List—Depreciation Guide are used. In determining third party liability, however, a different depreciation guide, the Joint Military/Industry Depreciation Guide is used instead. In most instances, the depreciation rates are the same in both guides, and claims personnel are not required to consult the Joint Military/Industry Depreciation Guide or alter the depreciation taken on items prior to dispatching demands. If, however, a carrier or contractor objects to the depreciation rate utilized for certain items, consult the Joint Military/Industry Depreciation Guide and use the depreciation rate found in that guide if it differs from the rate in the Allowance List-Depreciation Guide.