§ 117.625 - Black River (Port Huron).  


Latest version.
  • § 117.625 Black River .

    (

    a) For all drawbridges across the Black River, notice requesting the opening of a draw may be given to the dispatcher of the Port Huron Police Department. Public vessels of the United States, state or local vessels used for public safety, and vessels in distress shall be passed through each drawbridge on the river as soon as possible. (b) The draws

    Port Huron).

    (a) The draw of the Military Street

    bridge

    Bridge, mile 0.

    3, and Seventh Street bridge, mile 0.5, both at Port Huron,

    33, shall open on signal; except that, from May 1 through October 31, from

    9

    8 a.m. to

    5:30

    11 p.m.

    Monday through Saturday except Federal holidays,

    , seven days a week, the draw need

    be opened

    open only on the hour and half-hour

    and,

    for recreational vessels, or at any time when there are more than five vessels waiting for an opening, and from November 1 through

    November 30 and April 1 through April 30 from 4 p

    April 30 if at least 12-hours advance notice is given.

    (b) The draw of the Seventh Street Bridge, mile 0.50, shall open on signal; except that, from May 1 through October 31, from 8 a.m. to 8 a11 p.m., seven days a week, the draw shall open if at least three hours notice is given. From December 1 through March 31, the draw shall open if at least 24 hours need open only on the quarter-hour and three-quarter-hour for recreational vessels, or at any time when there are more than five vessels waiting for an opening, and from November 1 through April 30 if at least 12-hours advance notice is given.

    (c) The draw of the Tenth Street bridgeBridge, mile 0.9 at Port Huron94, shall open on signal -

    (1) From

    ; except that, from May 1 through October 31, from 8 a.m. to 11 p.m., seven days a week, the draw need open only on the hour and half-hour for recreational vessels, or at any time when there are more than five vessels waiting for an opening, and from 11 p.m. to 8 a.m.

    ,

    if at least

    one hours notice is given; (2) From April 1 through April 30 and

    1-hour advance notice is provided, and from November 1 through

    November

    April 30

    ,

    if at least

    three

    12-hours notice is given

    ; and

    .

    (

    3) From December 1 through March 31, if at least 24 hours notice is given.

    d) The draw of the Canadian National Railroad Bridge, mile 1.56, shall open on signal; except from November 1 through April 30 if at least 12-hours advance notice is given.

    [USCG-2017-1047, 83 FR 10619, Mar. 12, 2018]