§ 472.34 - Under what circumstances may a project continue if a partner withdraws?


Latest version.
  • (a) A project may continue despite the withdrawal of a partner that is unable to perform its role as outlined in the grant award document if all of the following conditions are met:

    (1) Written approval is given by the Secretary.

    (2) The partnership continues to meet the requirements in §472.2(b).

    (3) The partnership will be able to complete the remainder of the project.

    (4) The partner's withdrawal will not cause a change in the scope or objectives of the grant or cooperative agreement.

    (b) In determining that the condition in paragraph (a)(4) of this section is satisfied, the Secretary considers such factors as whether—

    (1) A similar new partner will sign the partnership agreement and agree to carry out the role of the withdrawing partner as described in the grant agreement;

    (2) One or more of the remaining partners will agree to carry out the role of the withdrawing partner as described in the grant agreement; or

    (3) One or more of the remaining partners will expand its activities as approved under the grant in order to compensate for the activities that would have been carried out under the grant agreement by the partner that is withdrawing without a change in the project's scope or objectives.

    (Authority: 20 U.S.C. 1211(a))

    [59 FR 1445, Jan. 10, 1994]