Table 1 to Subpart MMMM of Part 60—Model Rule—Increments of Progress and Compliance Schedules for Existing Sewage Sludge Incineration Units  


Latest version.
  • Comply with these increments of progressBy these datesa
    Increment 1—Submit final control plan(Dates to be specified in state plan)
    Increment 2—Final compliance(Dates to be specified in state plan)b

    aSite-specific schedules can be used at the discretion of the state.

    bThe date can be no later than 3 years after the effective date of state plan approval or March 21, 2016 for SSI units that commenced construction on or before October 14, 2010.