Table 5 to Subpart FFF of Part 62 - Generic Compliance Schedules and Increments of Progress  


Latest version.
  • Table 5 to Subpart FFF of Part 62 - Generic Compliance Schedules and Increments of Progress

    [Post-1987 MWCs]a b

    Affected facilities Increment 1
    Submit final control plan
    Increment 2
    Award
    contracts
    Increment 3
    Begin on-site construction
    Increment 4
    Complete on-site construction
    Increment 5
    Final compliance
    Affected facilities that commenced construction modification, or reconstruction after June 26, 1987:
    1. Emission limits for Hg, dioxin/furan NAc NAc NAc NAc 11/12/99 or 1 year after permit issuanced e
    2. Emission limits for SO2, HCl, PM, Pb, Cd, opacity CO, NOX January 11, 1999 05/18/99 11/16/99 11/19/00 12/19/00.

    [63 FR 63202, Nov. 12, 1998, as amended at 65 FR 33468, May 24, 2000]