Table 6 of Subpart FFF to Part 62 - Site-Specific Compliance Schedules and Increments of Progress a


Latest version.
  • Affected facilities at the following MWC sitesCity, StateIncrement 1
  • Submit final control plan
  • Increment 2
  • Award contracts
  • Increment 3
  • Begin on-site construction
  • Increment 4
  • Complete on-site construction
  • Increment 5
  • Final compliance c
  • Stanislaus Resource Recovery FacilityCrows Landing, CaliforniaJanuary 11, 199901/19/0005/19/0011/19/0012/19/00Southeast Resource Recovery FacilityLong Beach, CaliforniaJanuary 11, 199904/30/9910/31/9904/30/0012/19/00All large MWC unitsMaineJanuary 11, 199901/01/9907/01/9909/01/0012/19/00Baltimore RescoBaltimore, MarylandJanuary 11, 1999January 11, 1999January 11, 199909/01/0012/19/00All large MWC unitsNew Jersey bJanuary 11, 199905/18/9911/14/9911/19/0012/19/00American Ref-FuelDelaware County, Pennsylvania11/01/9805/18/9911/14/9911/19/0012/19/00Montenay Energy ResourceMontgomery County, Pennsylvania11/01/9805/18/9911/14/9911/19/0012/19/00I-95 Energy/Resource Recovery FacilityLorton, VirginiaJanuary 11, 199910/15/9903/01/0011/19/0012/19/00New Hanover County, Unit 3AWilmington, North Carolina09/15/9903/01/0007/01/0011/19/0012/19/00a These schedules have been reviewed and determined to be acceptable by EPA.b This schedule applies to HC1 SO2, PM, Pb, Cd, CO, and NOX. However, owners and operators of large MWC units in New Jersey have the option of reserving the portion of their control plan that addresses NOX. Owners and operators must submit the reserved portion to EPA by December 15, 1999.c The owner or operator of an affected facility that began construction, modification, or reconstruction after June 26, 1987 must achieve final compliance with the mercury and dioxins/furans limits within 1 year after promulgation of subpart FFF (i.e., by 11/12/99) or 1 year after permit issuance. Permit issuance is issuance of a revised construction permit or revised operating permit if a permit modification is required to retrofit controls. Final compliance must be achieved no later than December 19, 2000, even if the date “1 year after permit issuance” exceeds December 19, 2000.