Table 6 to Subpart FFF of Part 62 - Site-Specific Compliance Schedules and Increments of Progress a
Latest version.
-
Table 6 to Subpart FFF of Part 62 - Site-Specific Compliance Schedules and Increments of Progressa
Affected facilities at the following MWC sites City, State Increment 1
Submit final control planIncrement 2
Award contractsIncrement 3
Begin on-site constructionIncrement 4
Complete on-site constructionIncrement 5
Final compliancecStanislaus Resource Recovery Facility Crows Landing, California January 11, 1999 01/19/00 05/19/00 11/19/00 12/19/00 Southeast Resource Recovery Facility Long Beach, California January 11, 1999 04/30/99 10/31/99 04/30/00 12/19/00 All large MWC units Maine January 11, 1999 01/01/99 07/01/99 09/01/00 12/19/00 Baltimore Resco Baltimore, Maryland January 11, 1999 January 11, 1999 January 11, 1999 09/01/00 12/19/00 All large MWC units New Jerseyb January 11, 1999 05/18/99 11/14/99 11/19/00 12/19/00 American Ref-Fuel Delaware County, Pennsylvania 11/01/98 05/18/99 11/14/99 11/19/00 12/19/00 Montenay Energy Resource Montgomery County, Pennsylvania 11/01/98 05/18/99 11/14/99 11/19/00 12/19/00 I-95 Energy/Resource Recovery Facility Lorton, Virginia January 11, 1999 10/15/99 03/01/00 11/19/00 12/19/00 New Hanover County, Unit 3A Wilmington, North Carolina 09/15/99 03/01/00 07/01/00 11/19/00 12/19/00 [63 FR 63202, Nov. 12, 1998; 64 FR 17219, Apr. 8, 1999, as amended at 65 FR 33469, May 24, 2000]