Table 3 to Subpart GGG of Part 62 - Generic Compliance Schedule and Increments of Progress a  


Latest version.
  • Table 3 to Subpart GGG of Part 62 - Generic Compliance Schedule and Increments of Progressa

    Increment Date
    Increment 1 - Submit final control plan 1 year after initial NMOC emission rate report or the first annual emission rate report showing NMOC emissions ≥50 Mg/yr.b
    Increment 2 - Award Contracts 20 months after initial NMOC emission rate report or the first annual emission rate report showing NMOC emissions ≥50 Mg/yr.b
    Increment 3 - Begin on-site construction 24 months after initial NMOC emission rate report or the first annual emission rate report showing NMOC emissions ≥50 Mg/yr.b
    Increment 4 - Complete on-site construction 30 months after initial NMOC emission rate report or the first annual emission rate report showing NMOC emissions ≥50 Mg/yr.b
    Increment 5 - Final compliance 30 months after initial NMOC emission rate report or the first annual emission rate report showing NMOC emissions ≥50 Mg/yr.b