    As required in § 63.7131, you must submit each report in this table that applies to you.

    You must submit a . . . The report must contain . . . You must submit the report . . .
    1. Compliance report a. If there are no deviations from any emission limitations (emission limit, operating limit, opacity limit, and VE limit) that applies to you, a statement that there were no deviations from the emission limitations during the reporting period; Semiannually according to the requirements in § 63.7131(b).
    b. If there were no periods during which the CMS, including any operating parameter monitoring system, was out-of-control as specified in § 63.8(c)(7), a statement that there were no periods during which the CMS was out-of-control during the reporting period; Semiannually according to the requirements in § 63.7131(b).
    c. If you have a deviation from any emission limitation (emission limit, operating limit, opacity limit, and VE limit) during the reporting period, the report must contain the information in § 63.7131(d); Semiannually according to the requirements in § 63.7131(b).
    d. If there were periods during which the CMS, including any operating parameter monitoring system, was out-of-control, as specified in § 63.8(c)(7), the report must contain the information in § 63.7131(e); and Semiannually according to the requirements in § 63.7131(b).
    e. Before the relevant compliance date for your source as specified in § 63.7083(e), if you had a startup, shutdown or malfunction during the reporting period and you took actions consistent with your SSMP, the compliance report must include the information in § 63.10(d)(5)(i). On and after the relevant compliance date for your source as specified in § 63.7083(e), if you had a startup, shutdown or malfunction during the reporting period and you failed to meet an applicable standard, the compliance report must include the information in § 63.7131(c)(3) Semiannually according to the requirements in § 63.7131(b).
    2. Before the relevant compliance date for your source as specified in § 63.7083(e), an immediate startup, shutdown, and malfunction report if you had a startup, shutdown, or malfunction during the reporting period that is not consistent with your SSMP Actions taken for the event By fax or telephone within 2 working days after starting actions inconsistent with the SSMP.
    3. Before the relevant compliance date for your source as specified in § 63.7083(e), an immediate startup, shutdown, and malfunction report if you had a startup, shutdown, or malfunction during the reporting period that is not consistent with your SSMP The information in § 63.10(d)(5)(ii) By letter within 7 working days after the end of the event unless you have made alternative arrangements with the permitting authority. See § 63.10(d)(5)(ii).
    (4) Performance Test Report The information required in § 63.7(g) According to the requirements of § 63.7131.

    [85 FR 44987, July 24, 2020]