Table 3 to Subpart O of Part 63 - —Standards for CEVs  


Latest version.
  • Table 3 to Subpart O of Part 63—Standards for CEVs

    As required in § 63.362(e), for each CEV, you must meet the applicable standard in the following table:

    For each . . . For which . . . You must . . . You must comply with the standard . . .
    1. Existing CEV at a major source facility a. Not applicable i. Continuously reduce EtO emissions by 99.94 percent1 No later than April 5, 2027.
    2. Existing CEV at an area source facility a. Facility EtO use is at least 60 tpy i. Continuously reduce EtO emissions by 99.9 percent 1 2 No later than April 6, 2026.
    b. Facility EtO use is less than 60 tpy i. Continuously reduce EtO emissions by 99 percent 1 3 No later than April 5, 2027.
    3. New CEV at a major source facility a. Initial startup is on or before April 5, 2024 i. Continuously reduce EtO emissions by 99.94 percent1 No later than April 5, 2024.
    b. Initial startup is after April 5, 2024 i. Continuously reduce EtO emissions by 99.94 percent1 Upon startup of the source.
    4. New CEV at an area source facility a. Initial startup is on or before April 5, 2024, and facility EtO use is at least 60 tpy i. Continuously reduce EtO emissions by 99.9 percent 1 4 No later than April 5, 2024.
    b. Initial startup is on or before April 5, 2024, facility EtO use is less than 60 tpy i. Continuously reduce EtO emissions by 99 percent 1 5 No later than April 5, 2024.
    c. Initial startup is after April 5, 2024, and facility EtO use is at least 60 tpy i. Continuously reduce EtO emissions by 99.9 percent 1 4 Upon startup of the source.
    d. Initial startup is after April 5, 2024, facility EtO use is less than 60 tpy i. Continuously reduce EtO emissions by 99 percent 1 5 Upon startup of the source.