Code of Federal Regulations (Last Updated: November 8, 2024) |
Title 40 - Protection of Environment |
Chapter I—Environmental Protection Agency |
SubChapter C—Air Programs |
Part 63 - National Emission Standards for Hazardous Air Pollutants for Source Categories |
Subpart O - Ethylene Oxide Emissions Standards for Sterilization Facilities |
Table 5 to Subpart O of Part 63 - —Standards for Group 2 Room Air Emissions
Latest version.
-
Table 5 to Subpart O of Part 63—Standards for Group 2 Room Air Emissions
As required in § 63.362(g), for your collection of Group 2 room air emissions, you must meet the applicable standard in the following table:
For each . . . For which . . . You must . . . You must comply with the requirement(s) . . . 1. Existing collection of Group 2 room air emissions at a major source facility a. Not applicable i. Operate all areas of the facility that contain Group 2 room air emissions with PTE, with all exhaust gas streams being captured and routed to a control system. Also,
ii. Continuously reduce EtO emissions by 86 percent1No later than April 5, 2027. 2. Existing collection of Group 2 room air emissions at an area source facility a. Facility EtO use is at least 20 tpy i. Operate all areas of the facility that contain Group 2 room air emissions with PTE, with all exhaust gas streams being captured and routed to a control system.2 Also,
ii. Continuously reduce EtO emissions by 98 percent12No later than April 6, 2026. b. Facility EtO use is at least 4 tpy but less than 20 tpy i. Operate all areas of the facility that contain Group 2 room air emissions with PTE, with all exhaust gas streams being captured and routed to a control system.2 Also,
ii. Continuously reduce EtO emissions by 80 percent12No later than April 6, 2026. c. Facility EtO use is less than 4 tpy Lower the EtO concentration within each sterilization chamber to 1 ppm before the chamber can be opened3 No later than April 5, 2027. 3. New collection of Group 2 room air emissions at a major source facility a. Initial startup is on or before April 5, 2024 i. Operate all areas of the facility that contain Group 2 room air emissions with PTE, with all exhaust gas streams being captured and routed to a control system. Also,
ii. Continuously reduce EtO emissions by 86 percent1No later than April 5, 2024. b. Initial startup is after April 5, 2024 i. Operate all areas of the facility that contain Group 2 room air emissions with PTE, with all exhaust gas streams being captured and routed to a control system. Also,
ii. Continuously reduce EtO emissions by 86 percent1Upon startup of the source. 4. New collection of Group 2 room air emissions at an area source facility a. Initial startup is on or before April 5, 2024, and facility EtO use is at least 20 tpy i. Operate all areas of the facility that contain Group 2 room air emissions with PTE, with all exhaust gas streams being captured and routed to a control system.5 Also,
ii. Continuously reduce EtO emissions by 98 percent15No later than April 5, 2024. b. Initial startup is on or before April 5, 2024, and facility EtO use is less than 20 tpy i. Operate all areas of the facility that contain Group 2 room air emissions with PTE, with all exhaust gas streams being captured and routed to a control system.6 Also,
ii. Continuously reduce EtO emissions by 80 percent16No later than April 5, 2024. c. Initial startup is after April 5, 2024, and facility EtO use is at least 20 tpy i. Operate all areas of the facility that contain Group 2 room air emissions with PTE, with all exhaust gas streams being captured and routed to a control system.5 Also,
ii. Continuously reduce EtO emissions by 98 percent15Upon startup of the source. d. Initial startup is after April 5, 2024, and facility EtO use is less than 20 tpy i. Operate all areas of the facility that contain Group 2 room air emissions with PTE, with all exhaust gas streams being captured and routed to a control system.6 Also,
ii. Continuously reduce EtO emissions by 80 percent16Upon startup of the source.