Table 1 to Subpart VVVV of Part 63 - Compliance Dates for New and Existing Boat Manufacturing Facilities  


Latest version.
  • Table 1 to Subpart VVVV of Part 63 - Compliance Dates for New and Existing Boat Manufacturing Facilities

    As specified in § 63.5695, you must comply by the dates in the following table:

    If your facility is - And - Then you must comply by this date -
    1. An existing source Is a major source on or before August 22, 20011 August 23, 2004.
    2. An existing or new area source Becomes a major source after August 22, 20011 1 year after becoming a major source or August 22, 2002, whichever is later.
    3. A new source Is a major source at startup1 Upon startup or August 22, 2001, whichever is later.