Table 8 to Subpart VVVV of Part 63 - Applicability of General Provisions (40 CFR Part 63, Subpart A) to Subpart VVVV


Latest version.
  • Table 8 to Subpart VVVV of Part 63 - Applicability of General Provisions (40 CFR Part 63, Subpart A) to Subpart VVVV

    As specified in § 63.5773, you must comply with the applicable requirements of the General Provisions according to the following table:

    Citation Requirement Applies to
    subpart VVVV
    Explanation
    § 63.1(a) General Applicability Yes.
    § 63.1(b) Initial Applicability Determination Yes.
    § 63.1(c)(1) Applicability After Standard Established Yes.
    § 63.1(c)(2) Yes Area sources are not regulated by subpart VVVV.
    § 63.1(c)(3) No [Reserved].
    § 63.1(c)(4)-(5) Yes.
    § 63.1(d) No [Reserved].
    § 63.1(e) Applicability of Permit Program Yes.
    § 63.2 Definitions Yes Additional definitions are found in § 63.5779.
    § 63.3 Units and Abbreviations Yes.
    § 63.4(a) Prohibited Activities Yes.
    § 63.4(b)-(c) Circumvention/Severability Yes.
    § 63.5(a) Construction/Reconstruction Yes.
    § 63.5(b) Requirements for Existing, Newly Constructed, and Reconstructed Sources Yes.
    § 63.5(c) No [Reserved].
    § 63.5(d) Application for Approval of Construction/Reconstruction Yes.
    § 63.5(e) Approval of Construction/Reconstruction Yes.
    § 63.5(f) Approval of Construction/Reconstruction Based on prior State Review Yes.
    § 63.6(a) Compliance with Standards and Maintenance Requirements - Applicability Yes.
    § 63.6(b) Compliance Dates for New and Reconstructed Sources Yes § 63.695 specifies compliance dates, including the compliance date for new area sources that become major sources after the effective date of the rule.
    § 63.6(c) Compliance Dates for Existing Sources Yes § 63.5695 specifies compliance dates, including the compliance date for existing area sources that become major sources after the effective date of the rule.
    § 63.6(d) No [Reserved].
    § 63.6(e)(1)-(2) Operation and Maintenance Requirements No Operating requirements for open molding operations with add-on controls are specified in § 63.5725.
    § 63.6(e)(3) Startup, Shut Down, and Malfunction Plans No Only sources with add-on controls must complete startup, shutdown, and malfunction plans.
    § 63.6(f)(1) No.
    § 63.6(f)(2)-(3) Compliance with Nonopacity Emission Standards Yes.
    § 63.6(g) Use of an Alternative Nonopacity Emission Standard Yes.
    § 63.6(h) Compliance with Opacity/Visible Emissions Standards No Subpart VVVV does not specify opacity or visible emission standards.
    § 63.6(i) Extension of Compliance with Emission Standards Yes.
    § 63.6(j) Exemption from Compliance with Emission Standards Yes.
    § 63.7(a)(1) Performance Test Requirements Yes.
    § 63.7(a)(2) Dates for performance tests No § 63.5716 specifies performance test dates.
    § 63.7(a)(3) Performance testing at other times Yes.
    § 63.7(b)-(h) Other performance testing requirements Yes.
    § 63.8(a)(1)-(2) Monitoring Requirements - Applicability Yes All of § 63.8 applies only to sources with add-on controls. Additional monitoring requirements for sources with add-on controls are found in § 63.5725.
    § 63.8(a)(3) No [Reserved].
    § 63.8(a)(4) No Subpart VVVV does not refer directly or indirectly to § 63.11.
    § 63.8(b)(1) Conduct of Monitoring Yes.
    § 63.8(b)(2)-(3) Multiple Effluents and CMS Yes Applies to sources that use a CMS on the control device stack.
    § 63.8(c)(1)(i) and (iii) CMS Operation and Maintenance No References to startup, shutdown, malfunction are not applicable.
    § 63.8(c)(1)-(4) CMS Operation and Maintenance Yes Except those provisions in § 63.8(c)(1)(i) and (iii) as noted above.
    § 63.8(c)(5) Continuous Opacity Monitoring Systems (COMS) No Subpart VVVV does not have opacity or visible emission standards.
    § 63.8(c)(6)-(8) CMS Calibration Checks and Out-of-Control Periods Yes.
    § 63.8(d) Quality Control Program Yes Except those provisions of § 63.8(d)(3) regarding a startup, shutdown, malfunction plan as noted below.
    § 63.8(d)(3) Quality Control Program No No requirement for a startup, shutdown, malfunction plan.
    § 63.8(e) CMS Performance Evaluation Yes.
    § 63.8(f)(1)-(5) Use of an Alternative Monitoring Method Yes.
    § 63.8(f)(6) Alternative to Relative Accuracy Test Yes Applies only to sources that use continuous emission monitoring systems (CEMS).
    § 63.8(g) Data Reduction Yes.
    § 63.9(a) Notification Requirements - Applicability Yes.
    § 63.9(b) Initial Notifications Yes.
    § 63.9(c) Request for Compliance Extension Yes.
    § 63.9(d) Notification That a New Source Is Subject to Special Compliance Requirements Yes.
    § 63.9(e) Notification of Performance Test Yes Applies only to sources with add-on controls.
    § 63.9(f) Notification of Visible Emissions/Opacity Test No Subpart VVVV does not have opacity or visible emission standards.
    § 63.9(g)(1) Additional CMS Notifications - Date of CMS Performance Evaluation Yes Applies only to sources with add-on controls.
    § 63.9(g)(2) Use of COMS Data No Subpart VVVV does not require the use of COMS.
    § 63.9(g)(3) Alternative to Relative Accuracy Testing Yes Applies only to sources with CEMS.
    § 63.9(h) Notification of Compliance Status Yes.
    § 63.9(i) Adjustment of Deadlines Yes.
    § 63.9(j) Change in Previous Information Yes.
    § 63.10(a) Recordkeeping/Reporting - Applicability Yes.
    § 63.10(b)(1) General Recordkeeping Requirements Yes §§ 63.567 and 63.5770 specify additional recordkeeping requirements.
    § 63.10(b)(2)(i), (iii), (vi)-(xiv) General Recordkeeping Requirements Yes.
    § 63.10(b)(2)(ii), (iv), (v) Recordkeeping Relevant to Startup, Shutdown, and Malfunction Periods No.
    § 63.10(b)(3) Recordkeeping Requirements for Applicability Determinations Yes § 63.5686 specifies applicability determinations for non-major sources.
    § 63.10(c)(1)-(14) Additional Recordkeeping for Sources with CMS Yes Applies only to sources with add-on controls.
    § 63.10(c)(15) Additional Recordkeeping for Sources with CMS No No requirement for a startup, shutdown, malfunction plan.
    § 63.10(d)(1) General Reporting Requirements Yes § 63.5764 specifies additional reporting requirements.
    § 63.10(d)(2) Performance Test Results Yes § 63.5764 specifies additional requirements for reporting performance test results.
    § 63.10(d)(3) Opacity or Visible Emissions Observations No Subpart VVVV does not specify opacity or visible emission standards.
    § 63.10(d)(4) Progress Reports for Sources with Compliance Extensions Yes.
    § 63.10(d)(5) Startup, Shutdown, and Malfunction Reports No Applies only to sources with add-on controls.
    § 63.10(e)(1) Additional CMS Reports - General Yes Applies only to sources with add-on controls.
    § 63.10(e)(2) Reporting Results of CMS Performance Evaluations Yes Applies only to sources with add-on controls.
    § 63.10(e)(3) Excess Emissions/CMS Performance Reports Yes Applies only to sources with add-on controls.
    § 63.10(e)(4) COMS Data Reports No Subpart VVVV does not specify opacity or visible emission standards.
    § 63.10(f) Recordkeeping/Reporting Waiver Yes.
    § 63.11 Control Device Requirements - Applicability No Facilities subject to subpart VVVV do not use flares as control devices.
    § 63.12 State Authority and Delegations Yes § 63.5776 lists those sections of subpart A that are not delegated.
    § 63.13 Addresses Yes.
    § 63.14 Incorporation by Reference Yes.
    § 63.15 Availability of Information/Confidentiality Yes.

    [86 FR 66041, Nov. 19, 2021]